‹ Mar 2025 results
FY2025_VA_Bridge Maint - BMN
- Let date
- Wednesday, March 5, 2025
- CCSJ
- 0911-00-115
- District
- Lufkin
- County
- Angelina
- Highway
- Various
- Limits
- Various Locations Districtwide to .
- Classification
- Bridge Maintenance · Construction
- Project number
- C 911-00-115
- Working days
- 102
- DBE goal
- 0%
Bidders 14
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $1,096,640 | | |
| 1 |
BLACKSMITH VENTURES LLC Low bidder |
$821,221 |
-25.1% |
|
| 2 |
LAKEY, INC. |
$821,374 |
-25.1% |
+0.0% |
| 3 |
THK CONSTRUCTION LLC |
$868,991 |
-20.8% |
+5.8% |
| 4 |
BECK-REIT & SONS, LTD. |
$877,094 |
-20.0% |
+6.8% |
| 5 |
GARRET SHIELDS INFRASTRUCTURE |
$883,770 |
-19.4% |
+7.6% |
| 6 |
PREMIER CONTRACTORS LLC |
$889,191 |
-18.9% |
+8.3% |
| 7 |
BK FIELD OPERATIONS LLC |
$949,470 |
-13.4% |
+15.6% |
| 8 |
MB WESTERN INDUSTRIAL CONTRACTING CO. |
$985,719 |
-10.1% |
+20.0% |
| 9 |
ICOS MANAGEMENT, LLC |
$1,001,512 |
-8.7% |
+22.0% |
| 10 |
RHINO EQUITY, LLC |
$1,058,980 |
-3.4% |
+29.0% |
| 11 |
CROSS PLUS CONSTRUCTION, LLC |
$1,187,562 |
+8.3% |
+44.6% |
| 12 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
$1,253,255 |
+14.3% |
+52.6% |
| 13 |
SCOUT 5 CONSTRUCTION LLC |
$1,459,215 |
+33.1% |
+77.7% |
| 14 |
CRACKSEAL OF TEXAS, LLC |
$1,601,324 |
+46.0% |
+95.0% |
Bid tab: unit prices 12 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 BLACKSMITH VENT… | #2 LAKEY, INC. | #3 THK CONSTRUCTIO… | #4 BECK-REIT & SON… | #5 GARRET SHIELDS … | #6 PREMIER CONTRAC… | #7 BK FIELD OPERAT… | #8 MB WESTERN INDU… |
| 1 | 104-7006 |
REMOV CONC (RIPRAP) | 375 | SY |
$100.00 |
$50.00 |
$25.00 |
$25.00 |
$33.00 |
$50.00 |
$60.00 |
$75.00 |
$15.81 |
| 2 | 164-7001 |
BROADCAST SEED (PERM_RURAL_SAND) | 4,100 | SY |
$2.00 |
$1.00 |
$0.6200 |
$6.51 |
$1.00 |
$1.00 |
$8.00 |
$0.5000 |
$3.20 |
| 3 | 168-7001 |
VEGETATIVE WATERING | 82 | TGL |
$20.00 |
$10.00 |
$10.00 |
$20.00 |
$1.00 |
$100.00 |
$50.00 |
$25.00 |
$125.00 |
| 4 | 400-7010 |
CEM STABIL BKFL | 5 | CY |
$350.00 |
$1,000.00 |
$350.00 |
$1,500.00 |
$300.00 |
$300.00 |
$300.00 |
$750.00 |
$200.00 |
| 5 | 432-7045 |
RIPRAP (STONE PROTECTION)(24 IN) | 3,542 | CY |
$250.00 |
$208.00 |
$200.00 |
$185.00 |
$211.00 |
$200.00 |
$200.00 |
$242.00 |
$225.00 |
| 6 | 459-7010 |
GABIONS (3' X 3')(GALV) | 60 | CY |
$500.00 |
$300.00 |
$450.00 |
$250.00 |
$277.00 |
$300.00 |
$400.00 |
$240.00 |
$450.00 |
| 7 | 500-7001 |
MOBILIZATION | 1 | LS |
$100,000.00 |
$1.00 |
$30,000.00 |
$88,000.00 |
$80,088.00 |
$75,000.00 |
$80,000.00 |
$30,000.00 |
$100,000.00 |
| 8 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$2,000.00 |
$1.00 |
$5,000.00 |
$10,477.50 |
$1,000.00 |
$5,000.00 |
$1.00 |
$1.00 |
$1,000.00 |
| 9 | 505-7001 |
TMA (STATIONARY) | 47 | DAY |
$250.00 |
$350.00 |
$300.00 |
$275.00 |
$1.00 |
$300.00 |
$1.00 |
$1.00 |
$250.00 |
| 10 | 506-7039 |
TEMP SEDMT CONT FENCE (INSTALL) | 960 | LF |
$4.00 |
$15.00 |
$4.57 |
$6.00 |
$1.00 |
$6.00 |
$2.00 |
$2.00 |
$5.00 |
| 11 | 506-7041 |
TEMP SEDMT CONT FENCE (REMOVE) | 960 | LF |
$1.00 |
$1.00 |
$1.25 |
$2.00 |
$1.00 |
$1.00 |
$2.00 |
$1.00 |
$2.00 |
| 12 | 7020-7003 |
GEN DEBRIS REMOVE FROM UNDER BRIDGES | 60 | CY |
$125.00 |
$100.00 |
$30.00 |
$50.00 |
$150.00 |
$150.00 |
$200.00 |
$150.00 |
$150.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 14.