‹ Jun 2026 results
FY 27 ILLUMINATION @ VARIOUS LOCATIONS
- Let date
- Wednesday, June 3, 2026
- CCSJ
- 0910-00-157
- District
- Tyler
- County
- Smith
- Highway
- Various
- Limits
- VARIOUS LOCATIONS IN to TYLER DISTRICT
- Classification
- Safety Improvement Projects · Construction
- Project number
- STP 2026(786)HES
- Working days
- 85
- DBE goal
- 0%
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $726,421 | | |
| 1 |
VACA UNDERGROUND UTILITIES INC Low bidder |
$565,281 |
-22.2% |
|
| 2 |
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION |
$596,416 |
-17.9% |
+5.5% |
| 3 |
TEXAS TRAFFIC CONTROL SYSTEMS, INC. |
$630,419 |
-13.2% |
+11.5% |
| 4 |
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC |
$646,601 |
-11.0% |
+14.4% |
| 5 |
STRIPING TECHNOLOGY, L.P. |
$649,514 |
-10.6% |
+14.9% |
| 6 |
MARCOM'S MOWING SERVICE, LLC |
$659,178 |
-9.3% |
+16.6% |
| 7 |
CREACOM, INC. |
$664,232 |
-8.6% |
+17.5% |
| 8 |
JASCO |
$669,417 |
-7.8% |
+18.4% |
| 9 |
THIRD COAST SERVICES LLC |
$714,525 |
-1.6% |
+26.4% |
| 10 |
AMERICAN LIGHTING AND SIGNALIZATION, LLC |
$795,000 |
+9.4% |
+40.6% |
| 11 |
SELECT MAINTENANCE, L.L.C. |
$877,484 |
+20.8% |
+55.2% |
Bid tab: unit prices 14 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 VACA UNDERGROUN… | #2 NORTH TEXAS TRA… | #3 TEXAS TRAFFIC C… | #4 HIGHWAY INTELLI… | #5 STRIPING TECHNO… | #6 MARCOM'S MOWING… | #7 CREACOM, INC. | #8 JASCO |
| 1 | 416-7040 |
DRILL SHAFT (RDWY ILL POLE) (30 IN) | 370 | LF |
$335.00 |
$200.00 |
$275.00 |
$300.00 |
$205.64 |
$335.00 |
$300.00 |
$181.21 |
$220.00 |
| 2 | 500-7001 |
MOBILIZATION | 1 | LS |
$67,500.00 |
$55,000.00 |
$40,000.00 |
$50,000.00 |
$65,308.31 |
$35,000.00 |
$40,000.00 |
$46,496.08 |
$75,000.00 |
| 3 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 | MO |
$4,000.00 |
$2,000.00 |
$3,200.00 |
$5,000.00 |
$5,714.28 |
$3,485.00 |
$4,000.00 |
$8,851.69 |
$500.00 |
| 4 | 503-7001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 8 | DAY |
$100.00 |
$1,000.00 |
$325.00 |
$200.00 |
$122.00 |
$125.00 |
$100.00 |
$280.27 |
$300.00 |
| 5 | 505-7001 |
TMA (STATIONARY) | 60 | DAY |
$200.00 |
$140.00 |
$215.00 |
$200.00 |
$244.00 |
$300.00 |
$250.00 |
$470.17 |
$100.00 |
| 6 | 505-7003 |
TMA (MOBILE OPERATION) | 20 | DAY |
$200.00 |
$60.00 |
$200.00 |
$200.00 |
$781.46 |
$300.00 |
$250.00 |
$166.45 |
$100.00 |
| 7 | 610-7128 |
IN RD IL (TY SA) 40T-12 (250W EQ) LED | 17 | EA |
$5,000.00 |
$5,000.00 |
$4,500.00 |
$4,550.00 |
$5,107.86 |
$5,056.00 |
$5,400.00 |
$7,246.84 |
$5,250.00 |
| 8 | 610-7200 |
IN RD IL (TY SA) 50T-12 (400W EQ) LED | 20 | EA |
$6,500.00 |
$5,500.00 |
$4,900.00 |
$4,885.00 |
$5,533.64 |
$5,670.00 |
$5,800.00 |
$8,199.85 |
$5,900.00 |
| 9 | 618-7030 |
CONDT (PVC) (SCH 40) (2") | 5,395 | LF |
$14.00 |
$10.50 |
$10.00 |
$12.00 |
$12.05 |
$9.15 |
$10.00 |
$6.06 |
$16.25 |
| 10 | 618-7055 |
CONDT (PVC) (SCH 80) (2") (BORE) | 1,893 | LF |
$35.00 |
$15.00 |
$30.00 |
$25.00 |
$22.68 |
$24.50 |
$30.00 |
$14.20 |
$27.00 |
| 11 | 620-7007 |
ELEC CONDR (NO.8) BARE | 7,288 | LF |
$2.00 |
$2.25 |
$2.75 |
$2.50 |
$1.88 |
$2.75 |
$2.25 |
$1.47 |
$2.70 |
| 12 | 620-7008 |
ELEC CONDR (NO.8) INSULATED | 14,576 | LF |
$2.50 |
$2.50 |
$2.75 |
$2.75 |
$2.14 |
$3.00 |
$2.50 |
$1.96 |
$2.10 |
| 13 | 624-7002 |
GROUND BOX TY A (122311)W/APRON | 28 | EA |
$1,750.00 |
$1,100.00 |
$1,200.00 |
$1,300.00 |
$1,235.70 |
$1,420.50 |
$1,500.00 |
$1,022.68 |
$1,500.00 |
| 14 | 628-7009 |
ELC SRV TY A 120/240 060(NS)SS(E)SP(O) | 6 | EA |
$6,895.00 |
$7,500.00 |
$6,700.00 |
$7,500.00 |
$10,074.38 |
$8,250.00 |
$9,000.00 |
$9,660.66 |
$10,300.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.