‹ Jan 2026 results
Bridge Maintenance (2026) South Segment
- Let date
- Tuesday, January 6, 2026
- CCSJ
- 0906-00-292
- CSJs
- 0556-05-025, 0906-00-292
- District
- Odessa
- County
- Ector
- Highway
- Various
- Limits
- Districtwide to .
- Classification
- Bridge Maintenance · Construction
- Project number
- C 906-00-292
- Working days
- 151
- DBE goal
- 0%
Bidders 12
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $727,300 | | |
| 1 |
PREMIER CONTRACTORS LLC Low bidder |
$498,387 |
-31.5% |
|
| 2 |
BK FIELD OPERATIONS LLC |
$591,362 |
-18.7% |
+18.7% |
| 3 |
MPB, INC. |
$630,895 |
-13.3% |
+26.6% |
| 4 |
RELMCO, INC. |
$719,890 |
-1.0% |
+44.4% |
| 5 |
PATHFIELD INVESTMENTS LLC |
$723,778 |
-0.5% |
+45.2% |
| 6 |
BECK-REIT & SONS, LTD. |
$732,971 |
+0.8% |
+47.1% |
| 7 |
RAGLE CONSTRUCTION, INC. |
$781,040 |
+7.4% |
+56.7% |
| 8 |
TI-ZACK CONCRETE, LLC |
$784,600 |
+7.9% |
+57.4% |
| 9 |
BLACKSMITH VENTURES LLC |
$866,950 |
+19.2% |
+74.0% |
| 10 |
GREY SKY CONSTRUCTION LLC |
$941,450 |
+29.4% |
+88.9% |
| 11 |
SCR CIVIL CONSTRUCTION, LLC |
$977,390 |
+34.4% |
+96.1% |
| 12 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
$1,115,600 |
+53.4% |
+123.8% |
Bid tab: unit prices 21 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 PREMIER CONTRAC… | #2 BK FIELD OPERAT… | #3 MPB, INC. | #4 RELMCO, INC. | #5 PATHFIELD INVES… | #6 BECK-REIT & SON… | #7 RAGLE CONSTRUCT… | #8 TI-ZACK CONCRET… |
| 1 | 132-7005 |
EMBANK (FNL)(OC)(TY C) | 59 | CY |
$16.37 |
|
|
|
|
|
|
|
|
| 3 | 429-7007 |
CONC STR REPAIR (VERTICAL & OVERHEAD) | 50 | SF |
$150.00 |
|
|
|
|
|
|
|
|
| 7 | 459-7009 |
GABION MATTRESSES (GALV) (24 IN) | 95 | SY |
$200.00 |
|
|
|
|
|
|
|
|
| 8 | 459-7011 |
GABIONS (PVC)( 3FT X 3 FT) | 75 | CY |
$360.00 |
|
|
|
|
|
|
|
|
| 15 | 780-7002 |
CNC CRACK REPAIR (DISCRETE)(INJECT) | 25 | LF |
$50.00 |
|
|
|
|
|
|
|
|
| 1 | 132-7005 |
EMBANK (FNL)(OC)(TY C) | 59 | CY |
|
$100.00 |
$100.00 |
$250.00 |
$150.00 |
$110.00 |
$110.00 |
$85.00 |
$68.75 |
| 2 | 351-7001 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2") | 18 | SY |
$29.21 |
$100.00 |
$400.00 |
$400.00 |
$250.00 |
$760.00 |
$250.00 |
$550.00 |
$187.50 |
| 3 | 429-7007 |
CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,278 | SF |
$150.00 |
$200.00 |
$100.00 |
$100.00 |
$165.00 |
$200.00 |
$150.00 |
$125.00 |
$168.75 |
| 4 | 429-7009 |
CONC STR REPAIR (STANDARD) | 27 | SF |
$150.00 |
$200.00 |
$200.00 |
$85.00 |
$190.00 |
$240.00 |
$180.00 |
$190.00 |
$312.50 |
| 5 | 438-7001 |
CLEANING AND SEALING EXISTING JOINTS | 365 | LF |
$35.00 |
$45.00 |
$55.00 |
$37.00 |
$55.00 |
$25.00 |
$65.00 |
$42.00 |
$125.00 |
| 6 | 438-7007 |
CLEANING AND SEALING EXIST JOINTS (CL7) | 170 | LF |
$44.95 |
$45.00 |
$60.00 |
$106.00 |
$72.00 |
$65.00 |
$55.00 |
$23.00 |
$96.25 |
| 7 | 459-7009 |
GABION MATTRESSES (GALV) (24 IN) | 95 | SY |
|
$250.00 |
$225.00 |
$400.00 |
$225.00 |
$260.00 |
$310.00 |
$270.00 |
$193.75 |
| 8 | 459-7011 |
GABIONS (PVC)( 3FT X 3 FT) | 75 | CY |
|
$250.00 |
$400.00 |
$500.00 |
$350.00 |
$300.00 |
$500.00 |
$310.00 |
$687.50 |
| 9 | 480-7001 |
CLEAN EXIST CULVERTS | 13 | EA |
$3,000.00 |
$650.00 |
$5,000.00 |
$5,225.00 |
$4,500.00 |
$1,500.00 |
$9,500.00 |
$1,900.00 |
$1,875.00 |
| 10 | 500-7001 |
MOBILIZATION | 1 | LS |
$61,014.63 |
$50,000.00 |
$55,000.00 |
$57,000.00 |
$60,000.00 |
$70,000.00 |
$85,000.00 |
$78,000.00 |
$12,500.00 |
| 11 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 | MO |
$15,000.00 |
$1.00 |
$1.00 |
$750.00 |
$5,000.00 |
$1,000.00 |
$1,200.00 |
$15,000.00 |
$9,375.00 |
| 12 | 503-7001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 140 | DAY |
$130.00 |
$1.00 |
$1.00 |
$50.00 |
$200.00 |
$1.00 |
$11.00 |
$10.00 |
$125.00 |
| 13 | 505-7001 |
TMA (STATIONARY) | 263 | DAY |
$200.00 |
$1.00 |
$1.00 |
$100.00 |
$200.00 |
$1.00 |
$11.00 |
$10.00 |
$125.00 |
| 14 | 778-7002 |
CONCRETE RAIL REPAIR (MISC) | 80 | LF |
$95.97 |
$150.00 |
$500.00 |
$295.00 |
$500.00 |
$280.00 |
$300.00 |
$250.00 |
$166.25 |
| 15 | 780-7002 |
CNC CRACK REPAIR (DISCRETE)(INJECT) | 50 | LF |
$50.00 |
$60.00 |
$140.00 |
$105.00 |
$80.00 |
$78.00 |
$65.00 |
$175.00 |
$93.75 |
| 16 | 787-7001 |
REPLACING ELASTOMERIC BEARING PADS | 24 | EA |
$6,000.00 |
$3,500.00 |
$7,500.00 |
$7,000.00 |
$4,500.00 |
$10,000.00 |
$6,887.00 |
$10,500.00 |
$9,375.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 12.