BRIDGE MAINTENANCE
- Let date
- Friday, January 5, 2024
- CCSJ
- 0904-00-232
- District
- Amarillo
- County
- Potter
- Highway
- US 60
- Limits
- DISTRICTWIDE
- Classification
- Construction
- Project number
- BR 2024(520)
- Working days
- 67
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,212,543 | ||
| 1 | DCC CONSTRUCTION AND SERVICES, L.L.C. Low bidder | $1,635,105 | +34.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DCC CONSTRUCTIO… |
|---|---|---|---|---|---|---|
| 1 | 428-6001 | PENETRATING CONCRETE SURFACE TREATMENT | 39,080 | SY | $7.00 | $20.00 |
| 2 | 438-6009 | CLEANING EXISTING JOINTS | 5,403 | LF | $11.00 | $35.00 |
| 3 | 500-6001 | MOBILIZATION | 1 | LS | $90,000.00 | $200,000.00 |
| 4 | 502-6025 | BARR, SIGNS, TRAFFIC HANDLING | 56 | EA | $3,000.00 | $2,000.00 |
| 5 | 764-6001 | DRAIN INLET CLEANING | 87 | EA | $200.00 | $100.00 |
| 6 | 764-6004 | DOWNSPOUT CLEANING | 77 | EA | $750.00 | $100.00 |
| 7 | 6001-6001 | PORTABLE CHANGEABLE MESSAGE SIGN | 65 | DAY | $110.00 | $200.00 |
| 8 | 6185-6002 | TMA (STATIONARY) | 65 | DAY | $300.00 | $400.00 |
| 9 | 7309-6001 | CLEANING STRUCTURE (BENT) | 185 | EA | $1,750.00 | $1,000.00 |
| 10 | 7309-6002 | CLEANING STRUCTURE (ABUTMENT) | 112 | EA | $1,750.00 | $1,000.00 |