| 1 | 100-6008 |
PREPARING ROW (TREE) (0" TO 6" DIA) | 2 | EA |
$400.00 |
$50.00 |
$10,000.00 |
$4,000.00 |
$1,000.00 |
$950.00 |
| 2 | 132-6003 |
EMBANKMENT (FINAL)(ORD COMP)(TY B) | 20 | CY |
$122.00 |
$50.00 |
$150.00 |
$200.00 |
$58.00 |
$150.00 |
| 3 | 401-6001 |
FLOWABLE BACKFILL | 1 | CY |
$500.00 |
$5,000.00 |
$500.00 |
$3,000.00 |
$980.00 |
$6,500.00 |
| 4 | 420-6158 |
CL C CONC(PILE ENCASEMENT) | 20 | LF |
$1,000.00 |
$1,000.00 |
$1,750.00 |
$1,000.00 |
$1,840.00 |
$1,650.00 |
| 5 | 427-6007 |
EPOXY WATERPROOF FINISH (TY X) | 4,213 | SF |
$15.00 |
$15.00 |
$16.00 |
$120.00 |
$19.00 |
$13.00 |
| 6 | 429-6002 |
CONC STR REPAIR (EPOXY MORTAR) | 4 | SF |
$400.00 |
$200.00 |
$500.00 |
$1,000.00 |
$500.00 |
$400.00 |
| 7 | 429-6007 |
CONC STR REPAIR (VERTICAL & OVERHEAD) | 822 | SF |
$300.00 |
$125.00 |
$300.00 |
$200.00 |
$240.00 |
$425.00 |
| 8 | 432-6002 |
RIPRAP (CONC)(5 IN) | 336 | CY |
$950.00 |
$500.00 |
$900.00 |
$750.00 |
$1,120.00 |
$800.00 |
| 9 | 438-6009 |
CLEANING EXISTING JOINTS | 1,608 | LF |
$20.00 |
$25.00 |
$35.00 |
$50.00 |
$20.00 |
$45.00 |
| 10 | 438-6010 |
RESIZING AND SEALING JOINTS | 82 | LF |
$100.00 |
$25.00 |
$100.00 |
$300.00 |
$88.00 |
$250.00 |
| 11 | 454-6008 |
HEADER TYPE EXPANSION JOINT | 3 | CF |
$900.00 |
$500.00 |
$1,200.00 |
$1,000.00 |
$5,600.00 |
$2,500.00 |
| 12 | 500-6001 |
MOBILIZATION | 1 | LS |
$152,000.00 |
$150,000.00 |
$145,000.00 |
$150,000.00 |
$179,000.00 |
$220,000.00 |
| 13 | 502-6025 |
BARR, SIGNS, TRAFFIC HANDLING | 17 | EA |
$12,000.00 |
$10,000.00 |
$3,500.00 |
$5,000.00 |
$5,000.00 |
$4,000.00 |
| 14 | 713-6005 |
CRACK CLEANING AND SEALING (JCP) | 690 | LF |
$28.00 |
$50.00 |
$25.00 |
$25.00 |
$31.00 |
$175.00 |
| 15 | 4206-6005 |
STEEL BRIDGE ZONE PAINTING (REF. NO. 4) | 45 | EA |
$700.00 |
$1,167.25 |
$1,200.00 |
$700.00 |
$1,740.00 |
$3,800.00 |
| 16 | 4206-6006 |
STEEL BRIDGE ZONE PAINTING (REF. NO. 5) | 104 | EA |
$1,500.00 |
$1,725.00 |
$1,800.00 |
$500.00 |
$2,806.00 |
$3,800.00 |
| 17 | 4207-6001 |
STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 | EA |
$75,000.00 |
$30,187.00 |
$31,000.00 |
$10,000.00 |
$40,900.00 |
$50,000.00 |
| 18 | 4207-6002 |
STEEL BRIDGE ZONE PAINTING REF STR #2 | 1 | EA |
$65,600.00 |
$50,140.00 |
$50,000.00 |
$10,000.00 |
$71,140.00 |
$50,000.00 |
| 19 | 4207-6003 |
STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 | EA |
$35,300.00 |
$30,032.25 |
$31,000.00 |
$10,000.00 |
$42,950.00 |
$50,000.00 |
| 20 | 4207-6004 |
STEEL BRIDGE ZONE PAINTING REF STR #4 | 1 | EA |
$15,000.00 |
$6,037.50 |
$7,500.00 |
$10,000.00 |
$8,700.00 |
$50,000.00 |
| 21 | 4207-6005 |
STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 | EA |
$22,400.00 |
$24,840.00 |
$31,000.00 |
$10,000.00 |
$43,710.00 |
$50,000.00 |
| 22 | 4207-6007 |
STEEL BRIDGE ZONE PAINTING REF STR #7 | 1 | EA |
$5,800.00 |
$21,275.00 |
$30,000.00 |
$10,000.00 |
$33,225.00 |
$50,000.00 |
| 23 | 4207-6008 |
STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 | EA |
$4,800.00 |
$20,700.00 |
$30,000.00 |
$10,000.00 |
$32,624.00 |
$50,000.00 |
| 24 | 6001-6001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 50 | DAY |
$200.00 |
$300.00 |
$200.00 |
$10.00 |
$160.00 |
$125.00 |
| 25 | 6185-6002 |
TMA (STATIONARY) | 80 | DAY |
$350.00 |
$400.00 |
$250.00 |
$10.00 |
$450.00 |
$125.00 |
| 26 | 7309-6001 |
CLEANING STRUCTURE (BENT) | 30 | EA |
$1,300.00 |
$1,300.00 |
$1,000.00 |
$2,000.00 |
$1,345.00 |
$1,500.00 |
| 27 | 7309-6002 |
CLEANING STRUCTURE (ABUTMENT) | 18 | EA |
$1,300.00 |
$1,300.00 |
$1,000.00 |
$2,000.00 |
$1,345.00 |
$2,500.00 |