‹ Jun 2021 results
BICYCLE AND PEDESTRIAN IMPROVEMENTS
- Let date
- Thursday, June 3, 2021
- CCSJ
- 0581-01-159
- District
- Dallas
- County
- Dallas
- Highway
- SL 12
- Limits
- IH 35E to FERGUSON RD
- Classification
- Construction
- Project number
- F 2021(609)
- Working days
- 138
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $2,476,944 | | |
| 1 |
NEW WORLD CONTRACTING, LLC Low bidder |
$1,924,542 |
-22.3% |
|
| 2 |
HIGHWAY 19 CONSTRUCTION LLC |
$2,126,314 |
-14.2% |
+10.5% |
| 3 |
DBI SERVICES, LLC |
$2,184,697 |
-11.8% |
+13.5% |
| 4 |
PROJECT ALLIED RESOURCES, LLC |
$2,223,358 |
-10.2% |
+15.5% |
| 5 |
SJ&J CONSTRUCTION, LLC |
$2,258,055 |
-8.8% |
+17.3% |
| 6 |
TI-ZACK CONCRETE, INC. |
$2,265,377 |
-8.5% |
+17.7% |
| 7 |
ENCINO LANDSCAPE, INC. |
$2,383,580 |
-3.8% |
+23.9% |
| 8 |
ALTUS CONSTRUCTION LLC |
$2,459,478 |
-0.7% |
+27.8% |
| 9 |
O. TREVINO CONSTRUCTION, LLC |
$2,647,363 |
+6.9% |
+37.6% |
| 10 |
HQS CONSTRUCTION LLC |
$2,755,342 |
+11.2% |
+43.2% |
| 11 |
FNH CONSTRUCTION, LLC |
$2,784,332 |
+12.4% |
+44.7% |
Bid tab: unit prices 43 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 NEW WORLD CONTR… | #2 HIGHWAY 19 CONS… | #3 DBI SERVICES, L… | #4 PROJECT ALLIED … | #5 SJ&J CONSTRUCTI… | #6 TI-ZACK CONCRET… | #7 ENCINO LANDSCAP… | #8 ALTUS CONSTRUCT… |
| 1 | 100-6002 |
PREPARING ROW | 91 | STA |
$3,000.00 |
$1,408.00 |
$1,000.00 |
$1,800.00 |
$726.00 |
$1,500.00 |
$900.00 |
$5,444.00 |
$1,853.84 |
| 2 | 104-6015 |
REMOVING CONC (SIDEWALKS) | 263 | SY |
$15.00 |
$8.00 |
$25.00 |
$20.00 |
$25.00 |
$25.00 |
$25.00 |
$20.00 |
$18.54 |
| 3 | 104-6021 |
REMOVING CONC (CURB) | 292 | LF |
$5.00 |
$10.00 |
$10.00 |
$15.00 |
$8.80 |
$8.00 |
$10.00 |
$20.00 |
$12.36 |
| 4 | 104-6028 |
REMOVING CONC (MISC) | 33 | SY |
$45.00 |
$19.00 |
$25.00 |
$20.00 |
$67.00 |
$35.00 |
$85.00 |
$30.00 |
$61.79 |
| 5 | 104-6044 |
REMOVING CONC (FLUME) | 6 | SY |
$15.25 |
$16.00 |
$100.00 |
$265.00 |
$19.90 |
$25.00 |
$85.00 |
$20.00 |
$247.18 |
| 6 | 110-6001 |
EXCAVATION (ROADWAY) | 493 | CY |
$10.00 |
$36.00 |
$15.00 |
$20.00 |
$23.30 |
$9.00 |
$45.00 |
$20.00 |
$30.85 |
| 7 | 132-6026 |
EMBANKMENT (FINAL) (DENS CONT) (TY C2) | 258 | CY |
$20.00 |
$47.00 |
$30.00 |
$30.00 |
$48.80 |
$35.00 |
$45.00 |
$20.00 |
$42.35 |
| 8 | 161-6017 |
COMPOST MANUF TOPSOIL (4") | 8,754 | SY |
$1.18 |
$3.40 |
$3.00 |
$5.00 |
$0.8700 |
$6.00 |
$4.00 |
$1.00 |
$2.47 |
| 9 | 162-6002 |
BLOCK SODDING | 8,754 | SY |
$4.00 |
$4.50 |
$5.00 |
$3.00 |
$6.80 |
$5.00 |
$4.00 |
$3.00 |
$3.36 |
| 10 | 164-6051 |
DRILL SEED (TEMP)(WARM OR COOL) | 1,751 | SY |
$0.1700 |
$1.25 |
$1.00 |
$2.00 |
$0.9600 |
$1.00 |
$1.00 |
$0.1100 |
$1.85 |
| 11 | 168-6001 |
VEGETATIVE WATERING | 1,562 | MG |
$7.50 |
$28.00 |
$50.00 |
$50.00 |
$51.00 |
$20.00 |
$13.00 |
$3.00 |
$1.24 |
| 12 | 403-6001 |
TEMPORARY SPL SHORING | 2,413 | SF |
$30.00 |
$28.00 |
$25.00 |
$40.00 |
$54.00 |
$35.00 |
$22.00 |
$15.00 |
$30.81 |
| 13 | 420-6011 |
CL B CONC (FLUME) | 24 | CY |
$500.00 |
$580.00 |
$600.00 |
$1,800.00 |
$1,150.00 |
$900.00 |
$1,000.00 |
$500.00 |
$745.23 |
| 14 | 423-6008 |
RETAINING WALL (CAST - IN - PLACE) | 4,526 | SF |
$100.00 |
$67.00 |
$70.00 |
$50.00 |
$73.00 |
$65.00 |
$60.00 |
$80.00 |
$98.39 |
| 15 | 432-6001 |
RIPRAP (CONC)(4 IN) | 29 | CY |
$450.00 |
$458.00 |
$500.00 |
$430.00 |
$976.00 |
$900.00 |
$1,000.00 |
$420.00 |
$418.63 |
| 16 | 432-6045 |
RIPRAP (MOW STRIP)(4 IN) | 8 | CY |
$500.00 |
$663.00 |
$500.00 |
$420.00 |
$1,110.00 |
$900.00 |
$1,000.00 |
$420.00 |
$418.63 |
| 17 | 500-6001 |
MOBILIZATION | 1 | LS |
$252,783.00 |
$200,000.00 |
$250,000.00 |
$220,000.00 |
$66,000.00 |
$400,000.00 |
$200,000.00 |
$180,000.00 |
$240,999.65 |
| 18 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 | MO |
$15,000.00 |
$12,471.00 |
$5,000.00 |
$10,000.00 |
$13,000.00 |
$8,000.00 |
$1,000.00 |
$7,500.00 |
$12,358.96 |
| 19 | 506-6020 |
CONSTRUCTION EXITS (INSTALL) (TY 1) | 221 | SY |
$25.00 |
$20.00 |
$30.00 |
$60.00 |
$29.30 |
$24.00 |
$20.00 |
$20.00 |
$22.96 |
| 20 | 506-6024 |
CONSTRUCTION EXITS (REMOVE) | 221 | SY |
$8.00 |
$9.00 |
$10.00 |
$18.00 |
$9.00 |
$12.00 |
$8.00 |
$5.00 |
$7.83 |
| 21 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 7,618 | LF |
$2.50 |
$2.00 |
$1.00 |
$1.50 |
$4.61 |
$3.00 |
$1.15 |
$5.00 |
$2.54 |
| 22 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 7,618 | LF |
$0.7500 |
$1.00 |
$1.00 |
$1.00 |
$1.03 |
$1.00 |
$0.5000 |
$1.00 |
$0.7400 |
| 23 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 2,699 | LF |
$4.25 |
$3.30 |
$3.00 |
$4.00 |
$6.70 |
$4.00 |
$4.00 |
$4.00 |
$4.25 |
| 24 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 2,699 | LF |
$1.25 |
$2.00 |
$1.00 |
$1.00 |
$1.43 |
$2.00 |
$0.5500 |
$1.00 |
$1.24 |
| 25 | 529-6002 |
CONC CURB (TY II) | 3,801 | LF |
$30.00 |
$26.00 |
$35.00 |
$30.00 |
$14.70 |
$17.00 |
$34.00 |
$20.00 |
$13.51 |
| 26 | 531-6001 |
CONC SIDEWALKS (4") | 9,899 | SY |
$52.00 |
$47.00 |
$56.00 |
$40.00 |
$62.00 |
$58.00 |
$100.00 |
$55.00 |
$51.71 |
| 27 | 531-6003 |
CONC SIDEWALKS (6") | 23 | SY |
$100.00 |
$65.00 |
$75.00 |
$100.00 |
$118.00 |
$60.00 |
$125.00 |
$75.00 |
$92.69 |
| 28 | 531-6004 |
CURB RAMPS (TY 1) | 1 | EA |
$1,900.00 |
$1,490.00 |
$1,100.00 |
$2,800.00 |
$2,380.00 |
$1,750.00 |
$1,750.00 |
$1,700.00 |
$1,667.57 |
| 29 | 531-6005 |
CURB RAMPS (TY 2) | 5 | EA |
$1,900.00 |
$2,036.00 |
$1,800.00 |
$1,800.00 |
$2,400.00 |
$2,000.00 |
$1,750.00 |
$1,700.00 |
$1,712.13 |
| 30 | 531-6010 |
CURB RAMPS (TY 7) | 4 | EA |
$1,900.00 |
$1,561.00 |
$1,100.00 |
$1,800.00 |
$2,510.00 |
$1,900.00 |
$1,750.00 |
$1,700.00 |
$2,131.39 |
| 31 | 531-6013 |
CURB RAMPS (TY 10) | 140 | EA |
$1,900.00 |
$1,140.00 |
$1,100.00 |
$1,800.00 |
$2,090.00 |
$1,700.00 |
$1,750.00 |
$1,800.00 |
$2,189.01 |
| 32 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 291 | LF |
$20.00 |
$22.00 |
$35.00 |
$45.00 |
$29.60 |
$31.00 |
$25.00 |
$20.00 |
$22.67 |
| 33 | 542-6001 |
REMOVE METAL BEAM GUARD FENCE | 291 | LF |
$3.00 |
$3.30 |
$2.00 |
$5.00 |
$6.60 |
$3.00 |
$1.50 |
$3.00 |
$3.55 |
| 34 | 542-6002 |
REMOVE TERMINAL ANCHOR SECTION | 1 | EA |
$200.00 |
$140.00 |
$120.00 |
$300.00 |
$220.00 |
$250.00 |
$130.00 |
$200.00 |
$299.02 |
| 35 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 2 | EA |
$2,600.00 |
$2,637.00 |
$2,280.00 |
$5,600.00 |
$3,060.00 |
$2,900.00 |
$2,500.00 |
$2,000.00 |
$2,686.52 |
| 36 | 544-6003 |
GUARDRAIL END TREATMENT (REMOVE) | 1 | EA |
$300.00 |
$281.00 |
$200.00 |
$300.00 |
$275.00 |
$300.00 |
$1.35 |
$350.00 |
$377.70 |
| 37 | 740-6005 |
ANTI - GRAFFITI COATNG(PERMNENT-TY III) | 4,526 | SF |
$1.00 |
$1.40 |
$10.00 |
$1.25 |
$1.47 |
$1.50 |
$1.35 |
$1.00 |
$1.54 |
| 38 | 5065-6001 |
CONCRETE SCUPPER | 33 | EA |
$2,500.00 |
$2,188.00 |
$1,500.00 |
$300.00 |
$2,650.00 |
$200.00 |
$165.00 |
$1,800.00 |
$7,336.74 |
| 39 | 5116-6001 |
AMPHIBIAN/REPTILE EXCLUSION FENCE INST | 987 | LF |
$3.00 |
$3.30 |
$3.00 |
$6.00 |
$6.30 |
$3.00 |
$5.50 |
$4.00 |
$3.71 |
| 40 | 5116-6002 |
AMPHIBIAN/REPTILE EXCLUSION FENCE REM | 987 | LF |
$1.00 |
$1.10 |
$1.00 |
$1.85 |
$1.74 |
$1.00 |
$5.50 |
$1.00 |
$1.24 |
| 41 | 6001-6002 |
PORTABLE CHANGEABLE MESSAGE SIGN | 6 | EA |
$12,500.00 |
$1,397.00 |
$10,000.00 |
$14,000.00 |
$5,200.00 |
$8,000.00 |
$1.00 |
$9,999.00 |
$4,943.58 |
| 42 | 6185-6002 |
TMA (STATIONARY) | 240 | DAY |
$200.00 |
$157.00 |
$200.00 |
$500.00 |
$196.00 |
$100.00 |
$1.00 |
$180.00 |
$173.03 |
| 43 | 6185-6005 |
TMA (MOBILE OPERATION) | 89 | DAY |
$150.00 |
$157.00 |
$500.00 |
$800.00 |
$198.00 |
$150.00 |
$1.00 |
$180.00 |
$308.97 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.