Bid tab 0409-03-013

Let Jan 6, 2023 · Houston · Waller Sign up free

‹ Jan 2023 results

BRIDGE MAINTENANCE

Let date
Friday, January 6, 2023
CCSJ
0409-03-013
District
Houston
County
Waller
Highway
FM 1488
Limits
AT CLEAR CREEK
Classification
Construction
Project number
BR 2023(241)
Working days
17

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$507,832
1 MB WESTERN INDUSTRIAL CONTRACTING COMPANY Low bidder $505,725 -0.4%
2 TALBRAN ENTERPRISES LLC $540,292 +6.4% +6.8%
3 NBG CONSTRUCTORS, INC. $581,611 +14.5% +15.0%
4 FNH CONSTRUCTION, LLC $673,030 +32.5% +33.1%
5 BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC $697,228 +37.3% +37.9%
6 RAGLE CONSTRUCTION, INC. $703,566 +38.5% +39.1%

Bid tab: unit prices 19 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MB WESTERN INDU…#2 TALBRAN ENTERPR…#3 NBG CONSTRUCTOR…#4 FNH CONSTRUCTIO…#5 BUILT RIGHT CON…#6 RAGLE CONSTRUCT…
1104-6009 REMOVING CONC (RIPRAP)340SY $28.00 $90.00 $60.00 $65.00 $100.00 $50.00 $50.00
2110-6002 EXCAVATION (CHANNEL)316CY $28.00 $55.00 $70.00 $50.00 $100.00 $30.00 $300.00
3162-6002 BLOCK SODDING91.5SY $8.00 $10.00 $20.00 $10.00 $20.00 $7.00 $12.00
4166-6001 FERTILIZER0.16AC $640.00 $3,000.00 $1,000.00 $500.00 $6,500.00 $1,100.00 $2,000.00
5168-6001 VEGETATIVE WATERING19MG $18.00 $100.00 $150.00 $100.00 $100.00 $80.00 $86.00
6400-6005 CEM STABIL BKFL454.8CY $200.00 $125.00 $220.00 $150.00 $350.00 $400.00 $107.00
7401-6001 FLOWABLE BACKFILL19CY $250.00 $350.00 $600.00 $275.00 $350.00 $500.00 $195.00
8403-6006 TEMPORARY SPL SHORING (COFFERDAM)732SF $80.00 $125.00 $40.00 $30.00 $85.00 $100.00 $66.00
9429-6007 CONC STR REPAIR (VERTICAL & OVERHEAD)11SF $900.00 $298.00 $280.00 $160.00 $1,000.00 $300.00 $300.00
10432-6002 RIPRAP (CONC)(5 IN)72.6CY $550.00 $800.00 $700.00 $1,200.00 $650.00 $1,000.00 $591.00
11438-6001 CLEANING AND SEALING EXISTING JOINTS235LF $35.00 $79.00 $80.00 $25.00 $100.00 $70.00 $65.00
12438-6009 CLEANING EXISTING JOINTS204LF $8.00 $26.00 $50.00 $20.00 $100.00 $60.00 $21.00
13459-6002 GABION MATTRESSES (GALV)458CY $300.00 $150.00 $280.00 $475.00 $300.00 $425.00 $398.00
14500-6001 MOBILIZATION1LS $39,105.00 $90,000.00 $55,000.00 $50,000.00 $60,000.00 $80,000.00 $70,000.00
15502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING2MO $6,000.00 $4,250.00 $5,000.00 $16,000.00 $8,500.00 $2,500.00 $65,000.00
16506-6001 ROCK FILTER DAMS (INSTALL) (TY 1)23LF $40.00 $40.00 $60.00 $60.00 $30.00 $50.00 $100.00
17506-6011 ROCK FILTER DAMS (REMOVE)23LF $12.00 $6.00 $60.00 $20.00 $20.00 $25.00 $20.00
18780-6006 CNC CRACK REPAIR (FLOOD)(GRAVITY)2,796SF $30.00 $15.80 $26.00 $16.00 $20.00 $6.00 $13.00
196185-6002 TMA (STATIONARY)3DAY $250.00 $596.00 $200.00 $150.00 $350.00 $350.00 $292.00