Bid tab 0331-04-069

Let Apr 9, 2020 · Pharr · Cameron Sign up free

‹ Apr 2020 results

BRIDGE MAINTENANCE

Let date
Thursday, April 9, 2020
CCSJ
0331-04-069
District
Pharr
County
Cameron
Highway
PR 100
Limits
AT QUEEN ISABELLA CAUSEWAY to STR #:_0331-04-005
Classification
Construction
Project number
BR 2020(709)
Working days
576

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$6,998,934
1 SOUTHERN ROAD & BRIDGE, LLC Low bidder $9,814,198 +40.2%
2 RUSSELL MARINE, LLC $10,919,499 +56.0% +11.3%
3 SCR CIVIL CONSTRUCTION, LLC $15,145,679 +116.4% +54.3%

Bid tab: unit prices 34 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SOUTHERN ROAD &…#2 RUSSELL MARINE,…#3 SCR CIVIL CONST…
1428-6001 PENETRATING CONCRETE SURFACE TREATMENT2,682SY $50.00 $22.00 $16.00 $60.00
2429-6003 CONC STR REPAIR(DECK REP(PART DEPTH))156SF $500.00 $335.00 $250.00 $220.00
3429-6005 CONC STR REPAIR(DECK REP (FULL DEPTH))24SF $750.00 $500.00 $500.00 $410.00
4429-6007 CONC STR REPAIR (VERTICAL & OVERHEAD)692SF $200.00 $440.00 $450.00 $275.00
5439-6013 MULTI-LAYER POLYMER OVERLAY5,280SY $125.00 $44.00 $38.00 $72.00
6446-6028 SPOT CLEAN & PAINT EXT STR(SPL PRT SYS)1LS $1,000,000.00 $750,000.00 $1,250,000.00 $1,910,000.00
7500-6001 MOBILIZATION1LS $500,000.00 $750,000.00 $942,350.00 $1,200,000.00
8502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING29MO $6,000.00 $10,000.00 $3,500.00 $3,900.00
9512-6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)6,900LF $40.00 $1.00 $40.00 $95.00
10512-6025 PORT CTB (MOVE)(SGL SLP)(TY 1)20,700LF $10.00 $0.1000 $5.00 $20.00
11512-6049 PORT CTB (REMOVE)(SGL SLP)(TY 1)6,900LF $10.00 $0.1000 $10.00 $22.00
12658-6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB400EA $25.00 $22.00 $22.00 $5.00
13658-6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB400EA $25.00 $22.00 $22.00 $5.00
14666-6159 RE PV MRK TY I(BLACK)4"(SHADOW)(100MIL)6,260LF $1.00 $1.00 $0.8500 $0.8500
15666-6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)6,260LF $0.5000 $0.5000 $0.7500 $0.8000
16666-6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)25,020LF $0.5000 $0.5000 $0.7500 $0.7500
17666-6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)25,020LF $0.5000 $0.5000 $0.7500 $0.7500
18672-6010 REFL PAV MRKR TY II-C-R320EA $3.00 $6.00 $5.00 $5.10
19677-6001 ELIM EXT PAV MRK & MRKS (4")50,640LF $0.5000 $0.5000 $0.6000 $0.6000
20678-6001 PAV SURF PREP FOR MRK (4")50,640LF $0.1000 $0.2000 $0.0500 $0.1000
21780-6002 CNC CRACK REPAIR (DISCRETE)(INJECT)300LF $100.00 $300.00 $275.00 $90.00
22785-6011 BRIDGE JOINT REPLACEMENT (SEJ)1,280LF $450.00 $444.00 $550.00 $1,000.00
234156-6001 CATHODIC SYS CONV TO BULK ANODES1LS $1,750,000.00 $3,000,000.00 $3,605,000.00 $3,235,000.00
244157-6001 REP CATHODIC PROT PILE JACKET (CRACK)2EA $750.00 $2,500.00 $1,800.00 $6,400.00
254157-6002 REP CATHODIC PROT PILE JACKET (HOLE)4EA $750.00 $4,000.00 $1,000.00 $4,900.00
264157-6003 REP CATH PROT PILE JKT (INSP JUNCT BOX)64EA $250.00 $1,250.00 $100.00 $800.00
274157-6004 REP CATH PROT PILE JACKET (WIRING)1EA $500.00 $5,000.00 $175.00 $2,000.00
284157-6005 REP CATH PROT PILE JACKET (ANODES)64EA $500.00 $2,500.00 $1,500.00 $2,600.00
294157-6006 REP C-P PILE JACKET (REPL JUNCT BOX)1EA $1,000.00 $5,000.00 $500.00 $3,000.00
304158-6001 C-P MONITORING SYSTEM1LS $150,000.00 $200,000.00 $235,000.00 $355,000.00
314159-6001 FRP JACKET ENCAPSULATION1LS $150,000.00 $650,000.00 $575,000.00 $406,000.00
324160-6001 QIC FENDER REPAIR1LS $825,000.00 $2,485,000.00 $2,000,000.00 $4,200,000.00
336001-6002 PORTABLE CHANGEABLE MESSAGE SIGN2EA $10,000.00 $100.00 $12,000.00 $25,000.00
346185-6002 TMA (STATIONARY)576DAY $180.00 $1.00 $235.00 $50.00