| 1 | 100-6002 |
PREPARING ROW | 11 | STA |
$1,000.00 |
$2,075.00 |
$1,000.00 |
$2,750.00 |
$10,000.00 |
$5,000.00 |
| 2 | 105-6038 |
REMOVING STAB BASE AND ASPH PAV (11") | 1,025 | SY |
$10.00 |
$8.10 |
$17.00 |
$28.00 |
$25.00 |
$20.00 |
| 3 | 110-6001 |
EXCAVATION (ROADWAY) | 1,871 | CY |
$10.00 |
$13.10 |
$10.00 |
$18.00 |
$19.00 |
$15.00 |
| 4 | 132-6002 |
EMBANKMENT (FINAL)(DENS CONT)(TY A) | 1,452 | CY |
$15.00 |
$9.55 |
$16.00 |
$17.00 |
$20.00 |
$20.00 |
| 5 | 160-6003 |
FURNISHING AND PLACING TOPSOIL (4") | 6,729 | SY |
$5.00 |
$1.80 |
$2.00 |
$4.20 |
$2.00 |
$2.00 |
| 6 | 162-6002 |
BLOCK SODDING | 584 | SY |
$10.00 |
$5.50 |
$5.50 |
$5.25 |
$5.50 |
$7.00 |
| 7 | 164-6003 |
BROADCAST SEED (PERM) (RURAL) (CLAY) | 6,111 | SY |
$0.7500 |
$0.2200 |
$0.2200 |
$0.2000 |
$0.2200 |
$0.3300 |
| 8 | 164-6009 |
BROADCAST SEED (TEMP) (WARM) | 3,056 | SY |
$0.5000 |
$0.1000 |
$0.2700 |
$0.2500 |
$0.2500 |
$0.3300 |
| 9 | 164-6011 |
BROADCAST SEED (TEMP) (COOL) | 3,056 | SY |
$0.5000 |
$0.2800 |
$0.2700 |
$0.2500 |
$0.2500 |
$0.3300 |
| 10 | 168-6001 |
VEGETATIVE WATERING | 34 | MG |
$50.00 |
$30.00 |
$30.00 |
$52.00 |
$22.00 |
$12.00 |
| 11 | 275-6001 |
CEMENT | 66 | TON |
$200.00 |
$175.00 |
$190.00 |
$200.00 |
$165.00 |
$200.00 |
| 12 | 275-6005 |
CEMENT TREAT (EXIST MATL)(12") | 3,900 | SY |
$10.00 |
$5.00 |
$3.50 |
$12.00 |
$7.50 |
$6.00 |
| 13 | 316-6401 |
AGGR (TY PE OR PL GR 4) | 122 | CY |
$200.00 |
$220.00 |
$190.00 |
$290.00 |
$300.00 |
$250.00 |
| 14 | 316-6436 |
ASPH (AC-15P OR AC-10-2TR) | 4,387 | GAL |
$10.00 |
$4.23 |
$3.10 |
$4.01 |
$4.50 |
$6.00 |
| 15 | 354-6023 |
PLANE ASPH CONC PAV(0" TO 4") | 7,340 | SY |
$5.00 |
$4.05 |
$3.85 |
$6.45 |
$3.50 |
$5.00 |
| 16 | 400-6005 |
CEM STABIL BKFL | 44 | CY |
$250.00 |
$210.00 |
$200.00 |
$225.00 |
$200.00 |
$200.00 |
| 17 | 464-6018 |
RC PIPE (CL IV)(24 IN) | 92 | LF |
$100.00 |
$101.00 |
$80.00 |
$103.00 |
$97.00 |
$100.00 |
| 18 | 467-6395 |
SET (TY II) (24 IN) (RCP) (6: 1) (P) | 2 | EA |
$2,500.00 |
$1,675.00 |
$1,100.00 |
$1,300.00 |
$1,600.00 |
$1,000.00 |
| 19 | 500-6001 |
MOBILIZATION | 1 | LS |
$125,000.00 |
$87,000.00 |
$110,000.00 |
$70,000.00 |
$130,000.00 |
$130,000.00 |
| 20 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$5,000.00 |
$2,200.00 |
$2,500.00 |
$2,600.00 |
$12,000.00 |
$15,000.00 |
| 21 | 506-6002 |
ROCK FILTER DAMS (INSTALL) (TY 2) | 88 | LF |
$45.00 |
$38.00 |
$38.00 |
$36.00 |
$36.00 |
$45.00 |
| 22 | 506-6011 |
ROCK FILTER DAMS (REMOVE) | 88 | LF |
$10.00 |
$10.00 |
$10.00 |
$9.50 |
$9.00 |
$13.00 |
| 23 | 506-6020 |
CONSTRUCTION EXITS (INSTALL) (TY 1) | 78 | SY |
$30.00 |
$35.50 |
$33.00 |
$34.00 |
$34.00 |
$30.00 |
| 24 | 506-6024 |
CONSTRUCTION EXITS (REMOVE) | 78 | SY |
$9.00 |
$10.00 |
$10.00 |
$9.50 |
$9.00 |
$13.00 |
| 25 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,564 | LF |
$2.00 |
$3.10 |
$3.25 |
$3.00 |
$3.00 |
$3.00 |
| 26 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,564 | LF |
$1.00 |
$0.9700 |
$1.00 |
$0.9000 |
$0.9000 |
$1.10 |
| 27 | 512-6067 |
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL) | 1,960 | LF |
$50.00 |
$15.63 |
$75.00 |
$70.00 |
$65.00 |
$80.00 |
| 28 | 512-6069 |
PTB (MOVE)(F SHAPE)(TY 1) OR (STL) | 3,220 | LF |
$10.00 |
$12.60 |
$1.00 |
$9.00 |
$8.00 |
$5.00 |
| 29 | 512-6071 |
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL) | 1,960 | LF |
$5.00 |
$9.42 |
$10.00 |
$11.00 |
$12.00 |
$7.00 |
| 30 | 530-6002 |
INTERSECTIONS (ACP) | 120 | SY |
$100.00 |
$266.84 |
$162.00 |
$145.00 |
$87.00 |
$80.00 |
| 31 | 533-6001 |
RUMBLE STRIPS (SHOULDER) | 2,183 | LF |
$2.00 |
$3.30 |
$1.25 |
$3.80 |
$2.50 |
$3.00 |
| 32 | 545-6003 |
CRASH CUSH ATTEN (MOVE & RESET) | 3 | EA |
$1,800.00 |
$2,100.00 |
$2,100.00 |
$2,000.00 |
$3,300.00 |
$4,000.00 |
| 33 | 545-6005 |
CRASH CUSH ATTEN (REMOVE) | 2 | EA |
$1,250.00 |
$1,000.00 |
$1,000.00 |
$950.00 |
$3,300.00 |
$2,000.00 |
| 34 | 545-6019 |
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 2 | EA |
$10,000.00 |
$9,625.00 |
$10,000.00 |
$9,200.00 |
$13,000.00 |
$12,000.00 |
| 35 | 644-6004 |
IN SM RD SN SUP&AM TY10BWG(1)SA(T) | 6 | EA |
$620.00 |
$850.00 |
$850.00 |
$810.00 |
$510.00 |
$800.00 |
| 36 | 644-6007 |
IN SM RD SN SUP&AM TY10BWG(1)SA(U) | 3 | EA |
$700.00 |
$855.00 |
$850.00 |
$815.00 |
$560.00 |
$800.00 |
| 37 | 644-6060 |
IN SM RD SN SUP&AM TYTWT(1)WS(P) | 7 | EA |
$365.00 |
$440.00 |
$440.00 |
$415.00 |
$270.00 |
$500.00 |
| 38 | 644-6076 |
REMOVE SM RD SN SUP&AM | 4 | EA |
$150.00 |
$80.00 |
$82.00 |
$110.00 |
$100.00 |
$150.00 |
| 39 | 658-6050 |
INSTL OM ASSM (OM-2Z)(FLX)SRF | 2 | EA |
$105.00 |
$80.00 |
$82.00 |
$80.00 |
$79.00 |
$400.00 |
| 40 | 662-6060 |
WK ZN PAV MRK REMOV (W)4"(BRK) | 660 | LF |
$2.00 |
$1.25 |
$2.20 |
$2.10 |
$1.20 |
$2.00 |
| 41 | 662-6063 |
WK ZN PAV MRK REMOV (W)4"(SLD) | 3,156 | LF |
$1.00 |
$1.05 |
$2.00 |
$1.60 |
$1.00 |
$2.00 |
| 42 | 662-6095 |
WK ZN PAV MRK REMOV (Y)4"(SLD) | 3,156 | LF |
$1.00 |
$1.05 |
$2.00 |
$1.60 |
$1.00 |
$2.00 |
| 43 | 666-6036 |
REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 1,416 | LF |
$2.00 |
$1.60 |
$1.32 |
$1.05 |
$1.60 |
$1.10 |
| 44 | 666-6300 |
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | 620 | LF |
$3.00 |
$1.11 |
$2.20 |
$2.10 |
$1.05 |
$2.20 |
| 45 | 666-6303 |
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | 2,136 | LF |
$3.00 |
$1.10 |
$1.65 |
$1.60 |
$1.05 |
$1.60 |
| 46 | 666-6315 |
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | 1,998 | LF |
$3.00 |
$1.12 |
$2.20 |
$2.10 |
$1.05 |
$2.20 |
| 47 | 668-6077 |
PREFAB PAV MRK TY C (W) (ARROW) | 2 | EA |
$220.00 |
$325.00 |
$264.00 |
$210.00 |
$310.00 |
$220.00 |
| 48 | 668-6081 |
PREFAB PAV MRK TY C (W) (U-LT ARROW) | 2 | EA |
$250.00 |
$440.00 |
$495.00 |
$475.00 |
$420.00 |
$500.00 |
| 49 | 668-6085 |
PREFAB PAV MRK TY C (W) (WORD) | 4 | EA |
$330.00 |
$335.00 |
$330.00 |
$315.00 |
$320.00 |
$330.00 |
| 50 | 672-6010 |
REFL PAV MRKR TY II-C-R | 100 | EA |
$5.00 |
$4.50 |
$5.50 |
$5.25 |
$4.30 |
$6.00 |
| 51 | 677-6001 |
ELIM EXT PAV MRK & MRKS (4") | 6,972 | LF |
$1.50 |
$0.6000 |
$0.4400 |
$0.4500 |
$0.6000 |
$0.4400 |
| 52 | 678-6001 |
PAV SURF PREP FOR MRK (4") | 4,754 | LF |
$0.5000 |
$0.1100 |
$0.1100 |
$0.1000 |
$0.1100 |
$0.1100 |
| 53 | 678-6004 |
PAV SURF PREP FOR MRK (8") | 1,416 | LF |
$0.5000 |
$0.2400 |
$0.1100 |
$0.1000 |
$0.2100 |
$0.1100 |
| 54 | 678-6009 |
PAV SURF PREP FOR MRK (ARROW) | 2 | EA |
$20.00 |
$11.00 |
$82.50 |
$80.00 |
$10.50 |
$100.00 |
| 55 | 678-6013 |
PAV SURF PREP FOR MRK (U/LT ARROW) | 2 | EA |
$25.00 |
$11.00 |
$110.00 |
$105.00 |
$10.50 |
$110.00 |
| 56 | 678-6016 |
PAV SURF PREP FOR MRK (WORD) | 4 | EA |
$25.00 |
$11.00 |
$82.50 |
$80.00 |
$10.50 |
$100.00 |
| 57 | 3077-6001 |
SP MIXES SP-B PG64-22 | 3,158 | TON |
$120.00 |
$107.25 |
$110.00 |
$118.00 |
$105.00 |
$115.00 |
| 58 | 3077-6014 |
SP MIXES SP-C PG64-22 (LEVEL-UP) | 395 | TON |
$200.00 |
$144.54 |
$130.00 |
$190.00 |
$125.00 |
$130.00 |
| 59 | 3077-6033 |
SP MIXES SP-C SAC-A PG76-22 | 1,207 | TON |
$150.00 |
$120.95 |
$120.00 |
$122.00 |
$116.00 |
$120.00 |
| 60 | 3077-6075 |
TACK COAT | 1,097 | GAL |
$10.00 |
$4.50 |
$3.20 |
$3.30 |
$6.00 |
$4.00 |
| 61 | 6185-6002 |
TMA (STATIONARY) | 122 | DAY |
$150.00 |
$25.00 |
$200.00 |
$150.00 |
$200.00 |
$300.00 |
| 62 | 6185-6005 |
TMA (MOBILE OPERATION) | 10 | DAY |
$50.00 |
$50.00 |
$132.00 |
$105.00 |
$75.00 |
$300.00 |