US 183 and IH35 ML (BMIP24)
- Let date
- Thursday, August 7, 2025
- CCSJ
- 0151-06-157
- District
- Austin
- County
- Travis
- Highway
- US 183
- Limits
- US 183 and IH 35 Mainlane to #14-227-0-0151-06-102.
- Classification
- Bridge Maintenance · Construction
- Project number
- BR 2025(954)
- Working days
- 30
- DBE goal
- 0%
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $806,400 | ||
| 1 | STRUCTURAL TECHNOLOGIES, LLC Low bidder | $498,058 | -38.2% | |
| 2 | SCR CIVIL CONSTRUCTION, LLC | $544,300 | -32.5% | +9.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRUCTURAL TECH… | #2 SCR CIVIL CONST… |
|---|---|---|---|---|---|---|---|
| 1 | 500-7001 | MOBILIZATION | 1 | LS | $73,100.00 | $45,000.00 | $54,400.00 |
| 2 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $10,000.00 | $2,700.00 | $14,000.00 |
| 3 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 30 | DAY | $250.00 | $125.00 | $600.00 |
| 4 | 505-7001 | TMA (STATIONARY) | 20 | DAY | $250.00 | $470.00 | $450.00 |
| 5 | 4032-7001 | MOISTURE TESTING | 2 | EA | $9,500.00 | $627.00 | $9,500.00 |
| 6 | 4032-7002 | SUPPLEMENTAL TENDON IMPREGNATION | 1 | EA | $40,000.00 | $36,000.00 | $44,000.00 |
| 7 | 4032-7003 | TENDON DRYING | 2 | HR | $3,200.00 | $7,000.00 | $5,400.00 |
| 8 | 4032-7004 | VOID CORRECTION/REMEDIAL GROUTING | 1 | EA | $35,000.00 | $8,500.00 | $18,900.00 |
| 9 | 4032-7005 | INTERNAL TENDON | 2 | EA | $135,000.00 | $70,000.00 | $58,450.00 |
| 10 | 4032-7006 | EXTERNAL TENDON | 2 | EA | $115,000.00 | $87,500.00 | $66,300.00 |