RECONSTRUCTION OF SAFETY REST AREA
- Let date
- Tuesday, May 7, 2019
- CCSJ
- 0133-03-047
- District
- Childress
- County
- Knox
- Highway
- US 82
- Limits
- WESTBOUND, EAST OF BENJAMIN
- Classification
- Construction
- Project number
- STP 2019(772)
- Working days
- 240
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $2,463,399 | ||
| 1 | ANTHONY INMAN CONSTRUCTION, INC. Low bidder | $2,268,300 | -7.9% | |
| 2 | WALDROP CONSTRUCTION CO., INC. | $2,429,020 | -1.4% | +7.1% |
| 3 | DCI CONTRACTING, INC. | $2,744,316 | +11.4% | +21.0% |