REPLACE TERMINAL ANCHOR SECTIONS ON GUARDRAIL
- Let date
- Wednesday, August 5, 2020
- CCSJ
- 0117-05-057
- District
- Bryan
- County
- Madison
- Highway
- SH 21
- Limits
- IH 45 to SAN JACINTO CL
- Classification
- Construction
- Project number
- STP 2B20(198)HES
- Working days
- 156
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $2,502,685 | ||
| 1 | ELITE CASTLE RESOURCES LLC Low bidder | $2,031,774 | -18.8% | |
| 2 | FNH CONSTRUCTION, LLC | $2,708,125 | +8.2% | +33.3% |
| 3 | VANN/ELLI, INC. | $3,140,635 | +25.5% | +54.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ELITE CASTLE RE… | #2 FNH CONSTRUCTIO… | #3 VANN/ELLI, INC. |
|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $164,577.55 | $125,000.00 | $255,000.00 | $250,000.00 |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 | MO | $4,349.43 | $2,500.00 | $8,500.00 | $15,000.00 |
| 3 | 540-6035 | MTL BM GD FEN TRANS (31"-28") | 605 | EA | $672.91 | $380.00 | $900.00 | $824.00 |
| 4 | 542-6001 | REMOVE METAL BEAM GUARD FENCE | 7,125 | LF | $2.46 | $2.75 | $3.00 | $3.00 |
| 5 | 542-6002 | REMOVE TERMINAL ANCHOR SECTION | 605 | EA | $254.62 | $50.00 | $250.00 | $300.00 |
| 6 | 544-6001 | GUARDRAIL END TREATMENT (INSTALL) | 605 | EA | $2,683.94 | $2,500.00 | $2,500.00 | $3,100.00 |
| 7 | 658-6062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 1,815 | EA | $32.70 | $22.00 | $50.00 | $56.00 |
| 8 | 6185-6002 | TMA (STATIONARY) | 157 | DAY | $181.19 | $300.00 | $250.00 | $300.00 |