Bid tab 0113-13-182

Let Mar 4, 2020 · Austin · Travis Sign up free

‹ Mar 2020 results

INSTALL MEDIAN BARRIER

Let date
Wednesday, March 4, 2020
CCSJ
0113-13-182
District
Austin
County
Travis
Highway
SL 360
Limits
0.733 MILES SOUTH OF RM 2222 to WALSH TARLTON LANE
Classification
Construction
Project number
STP 2020(621)HES
Working days
48

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,251,500
1 DAN WILLIAMS COMPANY Low bidder $1,310,000 +4.7%
2 MASSANA CONSTRUCTION INC. $1,426,987 +14.0% +8.9%
3 ALTUS CONSTRUCTION LLC $1,451,749 +16.0% +10.8%
4 CROSS PLUS CONSTRUCTION, LLC $1,656,407 +32.4% +26.4%
5 FNH CONSTRUCTION, LLC $1,702,930 +36.1% +30.0%
6 AUSTIN ENGINEERING CO., INC. $1,776,194 +41.9% +35.6%

Bid tab: unit prices 17 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 DAN WILLIAMS CO…#2 MASSANA CONSTRU…#3 ALTUS CONSTRUCT…#4 CROSS PLUS CONS…#5 FNH CONSTRUCTIO…#6 AUSTIN ENGINEER…
1132-6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B)1,540CY $25.00 $40.00 $32.00 $37.09 $35.00 $50.00 $25.00
2150-6001 BLADING55STA $140.00 $200.00 $140.00 $300.33 $1,233.00 $450.00 $140.00
3160-6003 FURNISHING AND PLACING TOPSOIL (4")11,000SY $1.00 $3.00 $4.80 $1.38 $5.00 $8.00 $1.80
4164-6007 BROADCAST SEED (PERM) (URBAN) (CLAY)11,000SY $0.2500 $0.2000 $0.3300 $0.2100 $3.00 $6.00 $0.2500
5168-6001 VEGETATIVE WATERING220MG $20.00 $15.00 $45.00 $26.49 $120.00 $50.00 $70.00
6169-6001 SOIL RETENTION BLANKETS (CL 1) (TY A)11,000SY $1.00 $1.50 $1.50 $0.9200 $3.00 $6.50 $1.80
7432-6045 RIPRAP (MOW STRIP)(4 IN)1,255CY $450.00 $380.00 $460.00 $445.01 $475.00 $500.00 $511.00
8500-6001 MOBILIZATION1LS $81,000.00 $130,004.00 $154,992.00 $143,057.00 $120,000.00 $170,000.00 $227,000.00
9502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING3MO $8,000.00 $30,000.00 $40,000.00 $26,492.14 $5,500.00 $15,000.00 $2,045.00
10506-6040 BIODEG EROSN CONT LOGS (INSTL) (8")2,500LF $3.00 $4.50 $9.00 $5.87 $9.00 $18.00 $5.50
11506-6043 BIODEG EROSN CONT LOGS (REMOVE)2,500LF $1.50 $1.00 $3.00 $2.65 $2.00 $9.00 $1.00
12543-6002 CABLE BARRIER SYSTEM (TL-4)32,860LF $10.00 $8.00 $9.25 $11.44 $12.20 $8.00 $16.50
13543-6020 CABLE BARRIER TERMINAL SECTION (TL-4)38EA $3,100.00 $4,350.00 $1,800.00 $2,914.28 $2,700.00 $3,000.00 $3,400.00
14543-6021 REMOVE CABLE BARRIER1,330LF $11.00 $2.70 $4.00 $3.97 $5.00 $5.00 $11.80
15644-6068 RELOCATE SM RD SN SUP&AM TY 10BWG5EA $700.00 $595.00 $500.00 $624.77 $65.00 $850.00 $670.00
166001-6001 PORTABLE CHANGEABLE MESSAGE SIGN116DAY $70.00 $125.00 $85.00 $99.35 $75.00 $150.00 $320.00
176185-6002 TMA (STATIONARY)90DAY $250.00 $250.00 $165.00 $397.38 $1,200.00 $550.00 $600.00