SH 288: DOW Barge Canal
- Let date
- Tuesday, December 2, 2025
- CCSJ
- 0111-08-129
- District
- Houston
- County
- Brazoria
- Highway
- SH 288
- Limits
- At DOW Barge Canal to .
- Classification
- Bridge Widening or Rehabilitation · Construction
- Project number
- F 2B25(339)
- Working days
- 94
- DBE goal
- 0%
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $706,848 | ||
| 1 | SOUTHERN ROAD & BRIDGE, LLC Low bidder | $1,115,100 | +57.8% | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $1,429,000 | +102.2% | +28.1% |
| 3 | RAGLE CONSTRUCTION, INC. | $1,431,300 | +102.5% | +28.4% |
| 4 | FORDE CONSTRUCTION COMPANY, INC. | $1,544,450 | +118.5% | +38.5% |
| 5 | SCR CIVIL CONSTRUCTION, LLC | $2,054,222 | +190.6% | +84.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SOUTHERN ROAD &… | #2 GARRET SHIELDS … | #3 RAGLE CONSTRUCT… | #4 FORDE CONSTRUCT… | #5 SCR CIVIL CONST… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 446-7010 | CLEAN & PAINT EXIST STR (SYSTEM III-A) | 1 | LS | $125,000.00 | $685,000.00 | $750,000.00 | $500,000.00 | $1,175,000.00 | $1,400,000.00 |
| 2 | 500-7001 | MOBILIZATION | 1 | LS | $64,260.00 | $115,000.00 | $100,000.00 | $140,000.00 | $150,000.00 | $205,000.00 |
| 3 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 | MO | $9,000.00 | $3,600.00 | $5,000.00 | $5,000.00 | $1,400.00 | $4,000.00 |
| 4 | 505-7001 | TMA (STATIONARY) | 22 | DAY | $300.00 | $100.00 | $500.00 | $100.00 | $300.00 | $1.00 |
| 5 | 4038-7001 | FENDER REPAIR | 1 | LS | $328,000.00 | $225,000.00 | $500,000.00 | $698,000.00 | $175,000.00 | $342,000.00 |
| 6 | 4049-7001 | INSTALL FENDER PILE ANODES | 66 | EA | $1,818.00 | $950.00 | $500.00 | $850.00 | $425.00 | $1,200.00 |