LANDSCAPE PLANTING AND IRRIGATION
- Let date
- Friday, January 8, 2021
- CCSJ
- 0073-09-040
- District
- San Antonio
- County
- Bexar
- Highway
- IH 37
- Limits
- 0.3 MILES S OF HARDY ROAD to 0.2 MILES N OF HARDY ROAD
- Classification
- Construction
- Project number
- NH 2021(226)
- Working days
- 54
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $328,444 | ||
| 1 | ENCINO LANDSCAPE, INC. Low bidder | $292,836 | -10.8% | |
| 2 | TIGHT LINE CONSTRUCTION, LLC | $296,751 | -9.6% | +1.3% |
| 3 | APEX LANDSCAPE & IRRIGATION, LLC | $329,946 | +0.5% | +12.7% |
| 4 | CENTRAL NORTH CONSTRUCTION, LLC | $424,010 | +29.1% | +44.8% |
| 5 | ALTUS CONSTRUCTION LLC | $523,101 | +59.3% | +78.6% |
| 6 | RESTEK, INC. | $561,592 | +71.0% | +91.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ENCINO LANDSCAP… | #2 TIGHT LINE CONS… | #3 APEX LANDSCAPE … | #4 CENTRAL NORTH C… | #5 ALTUS CONSTRUCT… | #6 RESTEK, INC. |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 161-6012 | GENERAL USE COMPOST | 1,027 | CY | $25.00 | $30.00 | $28.00 | $22.00 | $36.00 | $49.85 | $100.00 |
| 2 | 170-6001 | IRRIGATION SYSTEM | 1 | LS | $35,600.00 | $40,000.00 | $55,000.00 | $55,000.00 | $50,000.00 | $45,699.36 | $75,000.00 |
| 3 | 192-6004 | PLANT MATERIAL (5-GAL) | 535 | EA | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $55.40 | $60.00 |
| 4 | 192-6005 | PLANT MATERIAL (15-GAL) | 364 | EA | $125.00 | $125.00 | $125.00 | $130.00 | $125.00 | $204.33 | $175.00 |
| 5 | 192-6006 | PLANT MATERIAL (30-GAL) | 45 | EA | $225.00 | $250.00 | $225.00 | $260.00 | $500.00 | $401.56 | $300.00 |
| 6 | 192-6013 | MULCH | 9,224 | SY | $3.00 | $3.00 | $3.00 | $2.25 | $3.00 | $4.19 | $6.00 |
| 7 | 192-6016 | PLANT BED PREPARATION | 9,224 | SY | $3.00 | $2.00 | $2.00 | $2.00 | $2.75 | $2.09 | $2.00 |
| 8 | 193-6001 | PLANT MAINTENANCE | 36 | MO | $1,500.00 | $1,000.00 | $1,000.00 | $1,500.00 | $1,800.00 | $3,205.95 | $3,000.00 |
| 9 | 193-6007 | IRRIGATION SYSTEM OPER AND MAINT | 36 | MO | $1,500.00 | $500.00 | $500.00 | $1,000.00 | $1,600.00 | $1,923.57 | $1,500.00 |
| 10 | 500-6001 | MOBILIZATION | 1 | LS | $24,000.00 | $40,000.00 | $30,000.00 | $32,000.00 | $45,000.00 | $51,295.16 | $25,000.00 |
| 11 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO | $1,500.00 | $2,000.00 | $2,500.00 | $4,000.00 | $5,500.00 | $1,923.57 | $2,500.00 |
| 12 | 506-6040 | BIODEG EROSN CONT LOGS (INSTL) (8") | 100 | LF | $3.00 | $10.00 | $5.00 | $0.1000 | $10.00 | $4.82 | $10.00 |
| 13 | 506-6043 | BIODEG EROSN CONT LOGS (REMOVE) | 100 | LF | $5.00 | $1.00 | $1.00 | $0.1000 | $5.50 | $1.36 | $10.00 |
| 14 | 6185-6002 | TMA (STATIONARY) | 6 | DAY | $225.00 | $1.00 | $100.00 | $10.00 | $1,500.00 | $320.59 | $300.00 |