HAZARD ELIMINATION & SAFETY
- Let date
- Wednesday, June 5, 2024
- CCSJ
- 0073-02-088
- District
- San Antonio
- County
- Bexar
- Highway
- US 281
- Limits
- MARTHA RD. to BEXAR/ATASCOSA COUNTY LINE
- Classification
- Construction
- Project number
- STP 2B24(174)HES
- Working days
- 97
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $1,997,645 | | |
| 1 |
ROADWAY SPECIALTIES, INC. Low bidder |
$1,472,161 |
-26.3% |
|
| 2 |
SCOUT 5 CONSTRUCTION LLC |
$1,594,892 |
-20.2% |
+8.3% |
| 3 |
SCR CIVIL CONSTRUCTION, LLC |
$1,625,366 |
-18.6% |
+10.4% |
| 4 |
DAN WILLIAMS COMPANY |
$1,750,038 |
-12.4% |
+18.9% |
| 5 |
MASSANA CONSTRUCTION INC. |
$1,760,093 |
-11.9% |
+19.6% |
| 6 |
ROSS SA ENTERPRISE LLC |
$1,814,688 |
-9.2% |
+23.3% |
| 7 |
HAZMAT INTERNATIONAL, INC. |
$1,883,357 |
-5.7% |
+27.9% |
| 8 |
MB WESTERN INDUSTRIAL CONTRACTING CO. |
$1,977,342 |
-1.0% |
+34.3% |
| 9 |
HJC FARMS, INC. |
$2,284,688 |
+14.4% |
+55.2% |
| 10 |
AARON CONCRETE CONTRACTORS, LLC |
$2,318,978 |
+16.1% |
+57.5% |
| 11 |
FNH CONSTRUCTION, LLC |
$2,450,922 |
+22.7% |
+66.5% |
Bid tab: unit prices 17 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 ROADWAY SPECIAL… | #2 SCOUT 5 CONSTRU… | #3 SCR CIVIL CONST… | #4 DAN WILLIAMS CO… | #5 MASSANA CONSTRU… | #6 ROSS SA ENTERPR… | #7 HAZMAT INTERNAT… | #8 MB WESTERN INDU… |
| 1 | 132-6021 |
EMBANKMENT (VEHICLE)(ORD COMP)(TY C) | 306 | CY |
$34.40 |
$60.42 |
$0.0100 |
$40.00 |
$50.00 |
$55.00 |
$50.00 |
$55.00 |
$35.00 |
| 2 | 150-6002 |
BLADING | 256 | HR |
$199.97 |
$141.32 |
$0.0100 |
$100.00 |
$150.00 |
$90.00 |
$75.00 |
$150.00 |
$250.00 |
| 3 | 164-6035 |
DRILL SEEDING (PERM) (RURAL) (CLAY) | 29,225 | SY |
$0.2900 |
$0.2700 |
$0.0100 |
$0.2500 |
$0.2000 |
$0.2500 |
$0.5000 |
$0.5000 |
$0.2800 |
| 4 | 164-6051 |
DRILL SEED (TEMP)(WARM OR COOL) | 29,225 | SY |
$0.1900 |
$0.2700 |
$0.0100 |
$0.1500 |
$0.1800 |
$0.1500 |
$0.5000 |
$0.5000 |
$0.2600 |
| 5 | 168-6001 |
VEGETATIVE WATERING | 455.9 | MG |
$22.18 |
$66.02 |
$0.0100 |
$60.00 |
$8.00 |
$57.00 |
$100.00 |
$50.00 |
$175.00 |
| 6 | 169-6001 |
SOIL RETENTION BLANKETS (CL 1) (TY A) | 29,225 | SY |
$1.86 |
$2.15 |
$0.0100 |
$1.37 |
$1.20 |
$1.00 |
$2.50 |
$2.25 |
$1.70 |
| 7 | 432-6066 |
RIPRAP (CL A) (MOW STRIP) (3 IN) | 1,218 | CY |
$415.00 |
$351.58 |
$800.00 |
$540.00 |
$500.00 |
$400.00 |
$460.00 |
$366.00 |
$635.00 |
| 8 | 500-6001 |
MOBILIZATION | 1 | LS |
$175,860.01 |
$161,752.50 |
$75,000.00 |
$121,500.00 |
$175,000.00 |
$311,916.70 |
$85,000.00 |
$360,000.00 |
$250,000.00 |
| 9 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 | MO |
$10,530.88 |
$1,160.25 |
$0.0100 |
$4,800.00 |
$20,000.00 |
$12,500.00 |
$3,900.00 |
$17,000.00 |
$2,000.00 |
| 10 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 2,348 | LF |
$3.31 |
$3.04 |
$30.00 |
$4.60 |
$4.00 |
$3.50 |
$3.00 |
$8.00 |
$5.68 |
| 11 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 2,348 | LF |
$0.8000 |
$0.7400 |
$1.00 |
$1.15 |
$1.00 |
$2.00 |
$1.00 |
$2.00 |
$1.42 |
| 12 | 506-6040 |
BIODEG EROSN CONT LOGS (INSTL) (8") | 320 | LF |
$6.07 |
$3.37 |
$80.00 |
$5.75 |
$5.00 |
$6.00 |
$10.00 |
$15.00 |
$7.10 |
| 13 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 320 | LF |
$1.76 |
$1.89 |
$1.00 |
$1.15 |
$1.00 |
$2.00 |
$1.00 |
$6.00 |
$1.42 |
| 14 | 543-6002 |
CABLE BARRIER SYSTEM (TL-4) | 43,837 | LF |
$15.74 |
$11.39 |
$8.00 |
$11.60 |
$11.00 |
$13.00 |
$14.00 |
$12.50 |
$11.30 |
| 15 | 543-6020 |
CABLE BARRIER TERMINAL SECTION (TL-4) | 68 | EA |
$4,457.31 |
$2,217.54 |
$1,400.00 |
$2,000.00 |
$2,925.00 |
$2,500.00 |
$3,500.00 |
$3,000.00 |
$2,350.00 |
| 16 | 6001-6002 |
PORTABLE CHANGEABLE MESSAGE SIGN | 6 | EA |
$14,525.47 |
$2,593.50 |
$0.0100 |
$1,800.00 |
$5,000.00 |
$1,800.00 |
$2,000.00 |
$500.00 |
$5,000.00 |
| 17 | 6185-6002 |
TMA (STATIONARY) | 87 | DAY |
$235.78 |
$409.50 |
$0.0100 |
$338.00 |
$204.00 |
$150.00 |
$1,000.00 |
$200.00 |
$200.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.