Bid tab 0055-01-029

Let Feb 7, 2020 · Brownwood · Mills Sign up free

‹ Feb 2020 results

PROFILE CENTER & EDGELINE AND THERMO STRIPING

Let date
Friday, February 7, 2020
CCSJ
0055-01-029
District
Brownwood
County
Mills
Highway
US 84
Limits
DISTRICT WIDE
Classification
Construction
Project number
STP 2020(530)HES
Working days
85

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,792,837
1 DOUBLE A CONTRACTING, L.P. Low bidder $2,363,261 -15.4%
2 D. I. J. CONSTRUCTION, INC. $2,459,929 -11.9% +4.1%
3 L&L COMPANY $2,546,104 -8.8% +7.7%
4 TOTAL HIGHWAY MAINTENANCE, LLC $2,584,957 -7.4% +9.4%
5 STRIPE-A-ZONE, INC. $2,591,932 -7.2% +9.7%
6 CENTERLINE TECHNOLOGIES, LLC $2,656,424 -4.9% +12.4%
7 STRIPING TECHNOLOGY, L.P. $2,795,534 +0.1% +18.3%
8 TRP CONSTRUCTION GROUP, LLC $2,996,179 +7.3% +26.8%

Bid tab: unit prices 21 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 DOUBLE A CONTRA…#2 D. I. J. CONSTR…#3 L&L COMPANY#4 TOTAL HIGHWAY M…#5 STRIPE-A-ZONE, …#6 CENTERLINE TECH…#7 STRIPING TECHNO…#8 TRP CONSTRUCTIO…
1500-6001 MOBILIZATION1LS $50,000.00 $19,000.00 $55,000.00 $1.00 $45,000.00 $22,500.00 $1.00 $500.00 $40,000.00
2502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING5MO $2,500.00 $20.00 $1,000.00 $1.00 $2,500.00 $700.00 $1.00 $500.00 $500.00
3666-6033 REFL PAV MRK TY I (W)8"(LNDP)(100MIL)539LF $1.00 $0.8900 $2.00 $1.00 $1.40 $2.00 $0.5000 $1.00 $1.00
4666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)29,967LF $0.6000 $0.6500 $0.6000 $0.6000 $0.6700 $0.8000 $0.4800 $0.7200 $0.8500
5666-6141 REFL PAV MRK TY I (Y)12"(SLD)(100MIL)1,174LF $0.9000 $2.50 $4.50 $3.00 $2.50 $2.65 $3.00 $3.00 $2.75
6666-6282 REF PROF PAV MRK TY I(W)4"(SLD)(060MIL)1,287,178LF $0.5300 $0.3900 $0.4400 $0.4500 $0.4300 $0.4300 $0.4600 $0.5000 $0.4500
7666-6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)770,458LF $0.5600 $0.4600 $0.4900 $0.4900 $0.4600 $0.4300 $0.5000 $0.5000 $0.5500
8666-6291 REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)124,010LF $0.5600 $0.4800 $0.4900 $0.4900 $0.4800 $0.5200 $0.5000 $0.7500 $0.6000
9666-6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)83,295LF $0.3000 $0.2700 $0.2200 $0.2600 $0.3000 $0.4300 $0.2600 $0.3000 $0.3500
10666-6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)2,295,626LF $0.2500 $0.2300 $0.2200 $0.2500 $0.2600 $0.2650 $0.2590 $0.2650 $0.3100
11666-6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)219,090LF $0.2800 $0.2300 $0.2300 $0.2600 $0.3000 $0.2650 $0.2600 $0.3000 $0.3500
12666-6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)2,306,804LF $0.2500 $0.2300 $0.2300 $0.2500 $0.2600 $0.2650 $0.2590 $0.2750 $0.3100
13668-6076 PREFAB PAV MRK TY C (W) (24") (SLD)8,855LF $11.00 $11.00 $9.50 $11.00 $10.25 $11.40 $11.00 $11.35 $12.50
14668-6077 PREFAB PAV MRK TY C (W) (ARROW)118EA $250.00 $180.00 $170.00 $200.00 $180.00 $200.00 $200.00 $170.50 $200.00
15668-6078 PREFAB PAV MRK TY C (W) (DBL ARROW)6EA $400.00 $320.00 $270.00 $350.00 $290.00 $327.00 $250.00 $275.50 $250.00
16668-6085 PREFAB PAV MRK TY C (W) (WORD)77EA $250.00 $220.00 $250.00 $250.00 $240.00 $305.00 $250.00 $215.50 $250.00
17668-6089 PREFAB PAV MRK TY C (W) (RR XING)24EA $400.00 $420.00 $600.00 $450.00 $500.00 $685.00 $500.00 $485.50 $600.00
18668-6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI)78EA $30.00 $20.00 $50.00 $25.00 $33.00 $37.15 $30.00 $50.50 $45.00
19668-6108 PREFAB PAV MRK TY C (Y) (24") (SLD)2,011LF $11.00 $12.00 $8.00 $13.00 $10.25 $11.40 $14.00 $11.35 $12.50
206056-6002 PREFORMED CENTERLINE RUMBLE STRIP23,973LF $3.80 $4.19 $4.40 $4.00 $3.40 $3.45 $6.00 $5.25 $4.50
216185-6005 TMA (MOBILE OPERATION)170DAY $100.00 $1.00 $10.00 $1.00 $0.0100 $0.1000 $1.00 $50.00 $50.00