HAZARD ELIMINATION & SAFETY
- Let date
- Tuesday, June 27, 2023
- CCSJ
- 0050-04-030
- District
- Houston
- County
- Waller
- Highway
- SH 6
- Limits
- GRIMES C/L to US 290
- Classification
- Construction
- Project number
- STP 2023(562)HES
- Working days
- 127
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,897,349 | ||
| 1 | MASSANA CONSTRUCTION INC. Low bidder | $1,561,387 | -17.7% | |
| 2 | ROADWAY SPECIALTIES, INC. | $1,629,395 | -14.1% | +4.4% |
| 3 | GRATIOT CONSTRUCTION, LTD. | $1,734,228 | -8.6% | +11.1% |
| 4 | SCR CIVIL CONSTRUCTION, LLC | $1,802,386 | -5.0% | +15.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 MASSANA CONSTRU… | #2 ROADWAY SPECIAL… | #3 GRATIOT CONSTRU… | #4 SCR CIVIL CONST… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 110-6001 | EXCAVATION (ROADWAY) | 1,429 | CY | $21.00 | $21.00 | $4.29 | $16.00 | |
| 2 | 432-6045 | RIPRAP (MOW STRIP)(4 IN) | 1,429 | CY | $550.00 | $475.00 | $439.78 | $550.00 | |
| 3 | 500-6001 | MOBILIZATION | 1 | LS | $175,000.00 | $101,043.50 | $331,695.00 | $160,000.00 | |
| 4 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 | MO | $7,300.00 | $9,000.00 | $1,077.03 | $5,000.00 | |
| 5 | 543-6002 | CABLE BARRIER SYSTEM (TL-4) | 38,478 | LF | $15.00 | $10.50 | $12.66 | $13.00 | |
| 6 | 543-6020 | CABLE BARRIER TERMINAL SECTION (TL-4) | 64 | EA | $3,000.00 | $3,500.00 | $2,200.82 | $3,100.00 | |
| 7 | 644-6068 | RELOCATE SM RD SN SUP&AM TY 10BWG | 31 | EA | $600.00 | $600.00 | $543.43 | $500.00 | |
| 8 | 6185-6002 | TMA (STATIONARY) | 252 | DAY | $210.00 | $95.00 | $34.13 | $25.00 |