Bid tab 0049-14-013

Let Oct 1, 2020 · Bryan · Robertson Sign up free

‹ Oct 2020 results

SEAL COAT

Let date
Thursday, October 1, 2020
CCSJ
0049-14-013
District
Bryan
County
Robertson
Highway
FM 46
Limits
FALLS COUNTY LINE to SH 14
Classification
Construction
Project number
STP 2021(066)
Working days
112

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$11,411,211
1 D. I. J. CONSTRUCTION, INC. Low bidder $9,071,398 -20.5%
2 F. N. PLOCH CONSTRUCTION COMPANY, INC. $9,403,943 -17.6% +3.7%
3 BRANNAN PAVING CO., LTD. $9,994,190 -12.4% +10.2%
4 CLARK CONSTRUCTION OF TEXAS, INC. $10,167,704 -10.9% +12.1%
5 RONALD R. WAGNER & CO., LP $12,677,858 +11.1% +39.8%

Bid tab: unit prices 29 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 D. I. J. CONSTR…#2 F. N. PLOCH CON…#3 BRANNAN PAVING …#4 CLARK CONSTRUCT…#5 RONALD R. WAGNE…
1316-6017 ASPH (AC-20-5TR)1,750,378GAL $2.95 $2.35 $2.30 $2.27 $2.75 $3.35
2316-6124 AGGR(TY-PB GR-3 SAC-A)2,873CY $100.00 $87.00 $85.00 $94.63 $88.00 $101.48
3316-6404 AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)33,672CY $105.00 $92.00 $89.00 $99.83 $92.00 $101.48
4500-6001 MOBILIZATION1LS $750,000.00 $470,000.00 $850,000.00 $1,291,700.00 $750,000.00 $1,380,755.00
5502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING6MO $10,000.00 $16,500.00 $7,500.00 $15,000.00 $7,500.00 $32,464.00
6530-6003 INTERSECTIONS (SURF TREAT)37,497SY $2.66 $1.50 $1.85 $1.50 $2.75 $2.00
7530-6006 DRIVEWAYS (SURF TREAT)46,953SY $2.38 $0.9000 $1.85 $1.00 $2.75 $2.00
8530-6009 TURNOUTS (SURF TREAT)31,715SY $3.03 $0.9000 $1.85 $0.5000 $2.75 $2.00
9662-6109 WK ZN PAV MRK SHT TERM (TAB)TY W757EA $0.7300 $0.0100 $1.00 $0.0100 $0.0100 $1.50
10662-6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2162,046EA $0.7300 $0.0100 $1.00 $0.0100 $0.0100 $1.50
11666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)8,688LF $0.9500 $1.60 $2.65 $2.65 $2.65 $2.65
12666-6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL)4,261LF $6.90 $6.85 $5.70 $5.70 $5.70 $5.70
13666-6102 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)16EA $3.03 $30.00 $36.60 $36.60 $36.60 $36.60
14666-6167 REFL PAV MRK TY II (W) 4" (BRK)31LF $0.1700 $1.00 $0.2500 $0.2500 $0.2500 $0.2500
15666-6170 REFL PAV MRK TY II (W) 4" (SLD)2,760,724LF $0.1200 $0.1000 $0.1000 $0.1000 $0.1000 $0.1000
16666-6205 REFL PAV MRK TY II (Y) 4" (BRK)228,332LF $0.1300 $0.1200 $0.1200 $0.1200 $0.1200 $0.1200
17666-6207 REFL PAV MRK TY II (Y) 4" (SLD)1,868,982LF $0.1200 $0.1100 $0.1000 $0.1000 $0.1050 $0.1050
18668-6077 PREFAB PAV MRK TY C (W) (ARROW)15EA $232.00 $200.00 $245.75 $245.75 $245.75 $245.75
19668-6078 PREFAB PAV MRK TY C (W) (DBL ARROW)3EA $415.00 $350.00 $395.25 $395.25 $395.25 $395.25
20668-6085 PREFAB PAV MRK TY C (W) (WORD)47EA $312.00 $275.00 $350.40 $350.40 $350.40 $350.40
21668-6089 PREFAB PAV MRK TY C (W) (RR XING)15EA $700.00 $600.00 $900.00 $900.00 $900.00 $900.00
22672-6007 REFL PAV MRKR TY I-C439EA $3.37 $2.50 $2.60 $2.60 $2.60 $2.60
23672-6009 REFL PAV MRKR TY II-A-A34,914EA $3.17 $2.60 $2.60 $2.60 $2.60 $2.60
24672-6010 REFL PAV MRKR TY II-C-R439EA $3.00 $2.50 $2.60 $2.60 $2.60 $2.60
25677-6001 ELIM EXT PAV MRK & MRKS (4")937,782LF $0.3500 $0.2500 $0.2050 $0.2050 $0.2200 $0.2200
266056-6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP280LF $27.00 $20.00 $20.00 $20.00 $20.00 $20.00
276185-6002 TMA (STATIONARY)64DAY $300.00 $10.00 $1.00 $120.00 $0.0100 $500.00
286185-6005 TMA (MOBILE OPERATION)268DAY $250.00 $1.00 $1.00 $50.00 $0.0100 $500.00
29316-6157 AGGR(TY-PL GR-3LW SAC-A)2,873CY $100.00