| 1 | 161-6022 |
GENERAL USE COMPOST (4") | 51,852 | SY |
$4.50 |
$2.55 |
$3.00 |
| 2 | 170-6001 |
IRRIGATION SYSTEM | 1 | LS |
$50,000.00 |
$625,000.00 |
$275,000.00 |
| 3 | 192-6002 |
PLANT MATERIAL (1-GAL) | 6,321 | EA |
$8.00 |
$3.00 |
$10.00 |
| 4 | 192-6004 |
PLANT MATERIAL (5-GAL) | 21,630 | EA |
$25.00 |
$10.00 |
$30.00 |
| 5 | 192-6005 |
PLANT MATERIAL (15-GAL) | 3,162 | EA |
$130.00 |
$42.00 |
$115.00 |
| 6 | 192-6013 |
MULCH | 51,852 | SY |
$3.50 |
$2.00 |
$3.00 |
| 7 | 192-6016 |
PLANT BED PREPARATION | 51,852 | SY |
$3.00 |
$1.75 |
$2.00 |
| 8 | 193-6001 |
PLANT MAINTENANCE | 24 | MO |
$250.00 |
$4,100.00 |
$1,500.00 |
| 9 | 193-6003 |
PLANT REPLACEMENT (1-GAL) | 630 | EA |
$8.00 |
$0.0100 |
$1.00 |
| 10 | 193-6005 |
PLANT REPLACEMENT (5-GAL) | 2,100 | EA |
$25.00 |
$0.0100 |
$1.00 |
| 11 | 193-6007 |
IRRIGATION SYSTEM OPER AND MAINT | 24 | MO |
$150.00 |
$1,500.00 |
$2,500.00 |
| 12 | 193-6009 |
PLANT REPLACEMENT (15 GAL) | 300 | EA |
$130.00 |
$0.0100 |
$1.00 |
| 13 | 402-6001 |
TRENCH EXCAVATION PROTECTION | 50 | LF |
$10.00 |
$0.0100 |
$1.00 |
| 14 | 403-6001 |
TEMPORARY SPL SHORING | 50 | SF |
$10.00 |
$0.0100 |
$1.00 |
| 15 | 432-6002 |
RIPRAP (CONC)(5 IN) | 1 | CY |
$550.00 |
$0.0100 |
$500.00 |
| 16 | 500-6001 |
MOBILIZATION | 1 | LS |
$154,436.95 |
$166,000.00 |
$200,000.00 |
| 17 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 | MO |
$1,500.00 |
$3,580.10 |
$2,000.00 |
| 18 | 506-6035 |
SANDBAGS FOR EROSION CONTROL | 150 | EA |
$5.00 |
$0.0100 |
$1.00 |
| 19 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 200 | LF |
$2.50 |
$0.0100 |
$1.00 |
| 20 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 200 | LF |
$1.00 |
$0.0100 |
$1.00 |
| 21 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 10,718 | LF |
$4.00 |
$0.0100 |
$3.00 |
| 22 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 10,718 | LF |
$1.00 |
$0.0100 |
$1.00 |
| 23 | 1004-6001 |
TREE PROTECTION | 12 | EA |
$290.00 |
$250.00 |
$300.00 |
| 24 | 6185-6002 |
TMA (STATIONARY) | 29 | DAY |
$175.00 |
$0.0100 |
$1.00 |