INSTALLATION OF RUMBLE STRIPS
- Let date
- Tuesday, December 3, 2019
- CCSJ
- 0014-07-104
- District
- Waco
- County
- Hill
- Highway
- IH 35
- Limits
- SH 81 to MCLENNAN CO LINE, ETC
- Classification
- Construction
- Project number
- STP 2020(526)HES
- Working days
- 120
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,547,876 | ||
| 1 | SURFACE PREPARATION TECHNOLOGIES, LLC Low bidder | $1,195,738 | -22.7% | |
| 2 | TOTAL HIGHWAY MAINTENANCE, LLC | $1,363,018 | -11.9% | +14.0% |
| 3 | TRP CONSTRUCTION GROUP, LLC | $1,542,317 | -0.4% | +29.0% |
| 4 | STRIPE-A-ZONE, INC. | $1,636,492 | +5.7% | +36.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SURFACE PREPARA… | #2 TOTAL HIGHWAY M… | #3 TRP CONSTRUCTIO… | #4 STRIPE-A-ZONE, … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $115,000.00 | $225,000.00 | $120,000.00 | $132,500.00 | |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 | MO | $5,000.00 | $1,000.00 | $500.00 | $2,500.00 | |
| 3 | 533-6003 | RUMBLE STRIPS (SHOULDER) ASPHALT | 164,389 | LF | $0.1200 | $0.3500 | $0.4000 | $0.2500 | |
| 4 | 533-6005 | RUMBLE STRIPS (SHOULDER) CONCRETE | 1,311,435 | LF | $0.9400 | $0.6900 | $0.7400 | $0.8500 | |
| 5 | 6185-6003 | TMA (MOBILE OPERATION) | 3,120 | HR | $45.00 | $0.1000 | $65.00 | $75.00 |