Bid tab 0010-19-010

Let Sep 7, 2017 · Atlanta · Bowie

‹ Sep 2017 results

PROFILE CENTERLINE & EDGELINE MRKS

Let date
Thursday, September 7, 2017
CCSJ
0010-19-010
District
Atlanta
County
Bowie
Highway
FM 991
Limits
US 67 W to US 67 E
Classification
· Construction
Project number
STP 2018(037)HESG
Working days
137

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,925,668
1 STRIPE-A-ZONE, INC. Low bidder $2,282,447 -22.0%
2 STRIPING TECHNOLOGY, L.P. $2,316,705 -20.8% +1.5%
3 TRP CONSTRUCTION GROUP, LLC $3,262,731 +11.5% +42.9%
4 TOTAL HIGHWAY MAINTENANCE, LLC $3,427,164 +17.1% +50.2%
5 HIGHWAY GRAPHICS, LLC $4,503,953 +53.9% +97.3%

Bid tab: unit prices 28 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 STRIPE-A-ZONE, …#2 STRIPING TECHNO…#3 TRP CONSTRUCTIO…#4 TOTAL HIGHWAY M…#5 HIGHWAY GRAPHIC…
1500-6001 MOBILIZATION1LS $200,000.00 $0.1000 $30,000.00 $100,000.00 $75,000.00 $175,000.00
2502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING9MO $1,000.00 $0.1000 $500.00 $2,500.00 $2,500.00 $2,500.00
3666-6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL)4,185LF $1.00 $0.6500 $0.8200 $0.8500 $0.7500 $4.00
4666-6226 PAVEMENT SEALER 8"10,139LF $0.3000 $0.1500 $0.3500 $0.4000 $0.2500 $0.3500
5666-6285 REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)499,150LF $0.9500 $0.6100 $0.7850 $0.6000 $0.5400 $0.9000
6668-6076 PREFAB PAV MRK TY C (W) (24") (SLD)2,069LF $10.50 $10.60 $11.70 $10.00 $13.50 $15.00
7668-6077 PREFAB PAV MRK TY C (W) (ARROW)52EA $190.00 $175.00 $172.50 $200.00 $230.00 $500.00
8668-6084 PREFAB PAV MRK TY C (W) (NUMBER)3EA $125.00 $175.00 $165.50 $210.00 $80.75 $650.00
9668-6085 PREFAB PAV MRK TY C (W) (WORD)44EA $250.00 $260.00 $199.50 $240.00 $306.00 $650.00
10668-6089 PREFAB PAV MRK TY C (W) (RR XING)3EA $500.00 $550.00 $485.50 $600.00 $737.00 $1,500.00
11668-6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI)6EA $45.00 $35.00 $55.50 $50.00 $52.50 $650.00
12668-6108 PREFAB PAV MRK TY C (Y) (24") (SLD)2,290LF $11.00 $11.00 $11.70 $10.00 $11.50 $15.00
13672-6007 REFL PAV MRKR TY I-C1,058EA $2.50 $2.40 $2.30 $3.50 $2.80 $6.00
14672-6009 REFL PAV MRKR TY II-A-A17,986EA $2.50 $2.40 $2.30 $2.75 $2.80 $6.00
15677-6001 ELIM EXT PAV MRK & MRKS (4")10,139LF $0.6000 $0.3600 $0.4000 $0.7000 $0.3500 $3.00
166019-6004 PREFB PV MK W/WNTY TY B(W)4"(SLD)CNTST2,890LF $5.00 $4.60 $4.50 $5.00 $5.00 $8.00
176019-6012 PREFB PV MK W/WNTY TY B(Y)4"(SLD)CNTST3,875LF $5.00 $4.60 $4.50 $5.00 $5.00 $8.00
186056-6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP184,266LF $3.00 $2.75 $2.45 $4.00 $5.00 $4.75
196056-6002 PREFORMED CENTERLINE RUMBLE STRIP175,721LF $3.00 $2.75 $2.45 $4.00 $4.00 $4.75
206081-6007 REFL PAV MRK WET(W) 6" (SLD)499,150LF $0.2200 $0.2300 $0.1750 $0.3000 $0.3500 $0.5000
216149-6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL)749,923LF $0.4800 $0.4000 $0.4250 $0.5500 $0.5500 $0.8000
226149-6005 REFL PAV MRK AWT (W) 6" (BRK) (100MIL)16,918LF $0.4800 $0.5200 $0.4850 $0.6500 $0.6000 $1.25
236149-6007 REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)103,185LF $0.3200 $0.3000 $0.2800 $0.4200 $0.4000 $0.6500
246149-6008 REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)7,770LF $0.3800 $0.4000 $0.5000 $1.00 $0.4500 $0.9000
256149-6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)856,329LF $0.4800 $0.4000 $0.4250 $0.5500 $0.5500 $0.8000
266149-6011 REFL PAV MRK AWT (Y) 6" (BRK) (100MIL)82,654LF $0.4800 $0.4000 $0.4850 $0.6500 $0.6000 $1.25
276185-6002 TMA (STATIONARY)13DAY $250.00 $0.0100 $1.00 $600.00 $725.00 $750.00
286185-6003 TMA (MOBILE OPERATION)1,000HR $30.00 $0.0100 $1.00 $75.00 $85.00 $55.00