Bid code 6019-6012

PREFB PV MK W/WNTY TY B(Y)4"(SLD)CNTST · per LF

‹ All bid codes

$5.33Avg low bid / LF
$6.12Avg of all bids
$6.03Avg engineer's estimate
11Jobs · 72,790 LF

Average low bid by year

YearJobsQuantityAvg lowAvg all
202114,275$7.77$7.80
2020239,756$5.13$6.24
201936,864$6.90$5.65
201814,783$4.10$4.07
2017315,055$4.98$5.58
201612,057$4.13$4.63

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Jun 4, 20210914-33-068 HaysAustin4,275 LF $7.77J3 COMPANY, LLC
Aug 6, 20200569-04-020 HarrisonAtlanta446 LF $8.80STATELINE CONSTRUCTION, LLC
Jul 8, 20200275-01-215 PotterAmarillo39,310 LF $5.09GILVIN-TERRILL, LTD.
Dec 3, 20190084-01-090 MorrisAtlanta1,310 LF $4.15STRIPE-A-ZONE, INC.
Aug 6, 20190010-08-057 MorrisAtlanta604 LF $10.00STRIPING TECHNOLOGY, L.P.
Jun 5, 20196288-86-001 BowieAtlanta4,950 LF $7.25STRIPING TECHNOLOGY, L.P.
Sep 6, 20180062-03-042 CassAtlanta4,783 LF $4.10STRIPE-A-ZONE, INC.
Oct 18, 20176315-08-001 WebbLaredo9,700 LF $5.25TRP CONSTRUCTION GROUP, LLC
Sep 7, 20170010-19-010 BowieAtlanta3,875 LF $4.60STRIPE-A-ZONE, INC.
Feb 3, 20170010-07-050 TitusAtlanta1,480 LF $4.25STRIPING TECHNOLOGY, L.P.
Dec 1, 20160063-01-092 HarrisonAtlanta2,057 LF $4.13STRIPE-A-ZONE, INC.