Bid tab 0010-06-042

Let Mar 5, 2019 · Atlanta · Titus Sign up free

‹ Mar 2019 results

SAFETY TREAT FIXED OBJECTS

Let date
Tuesday, March 5, 2019
CCSJ
0010-06-042
District
Atlanta
County
Titus
Highway
US 67
Limits
BU 271 to FRANKLIN C/L
Classification
Construction
Project number
STP 2019(634)HES
Working days
240

Bidders 10

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$3,219,831
1 LONGVIEW BRIDGE AND ROAD, LTD. Low bidder $2,498,030 -22.4%
2 CDM HOLDINGS, LLC $2,526,922 -21.5% +1.2%
3 H. V. CAVER, INC. $2,531,621 -21.4% +1.3%
4 STATELINE CONSTRUCTION, LLC $2,578,154 -19.9% +3.2%
5 RAYFORD'S TRUCK & TRACTOR $2,684,166 -16.6% +7.5%
6 EAST TEXAS BRIDGE, INC. $2,769,526 -14.0% +10.9%
7 PIERCE R & B LLC $2,894,717 -10.1% +15.9%
8 HIGHWAY 19 CONSTRUCTION LLC $3,002,423 -6.8% +20.2%
9 TALBRAN ENTERPRISES LLC $3,091,853 -4.0% +23.8%
10 K.WEST GROUP, LLC $3,302,472 +2.6% +32.2%

Bid tab: unit prices 21 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 LONGVIEW BRIDGE…#2 CDM HOLDINGS, L…#3 H. V. CAVER, IN…#4 STATELINE CONST…#5 RAYFORD'S TRUCK…#6 EAST TEXAS BRID…#7 PIERCE R & B LLC#8 HIGHWAY 19 CONS…
1100-6002 PREPARING ROW146.02STA $3,000.00 $2,000.00 $800.00 $1,500.00 $1,200.00 $1,000.00 $2,500.00 $700.00 $1,000.00
2132-6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C)1,804CY $30.00 $20.00 $12.00 $22.00 $20.00 $30.00 $20.00 $30.00 $30.00
3150-6001 BLADING457.3STA $100.00 $225.00 $100.00 $75.00 $75.00 $150.00 $300.00 $225.00 $500.00
4164-6001 BROADCAST SEED (PERM) (RURAL) (SANDY)111,422SY $0.3500 $0.2100 $0.1000 $0.1900 $0.2500 $0.0500 $0.2500 $0.5000 $0.1900
5168-6001 VEGETATIVE WATERING1,768.1MG $35.00 $1.00 $1.00 $5.00 $5.00 $8.00 $7.00 $10.00 $30.00
6400-6007 CUT & RESTORE CONC PAVING301SY $180.00 $135.00 $140.00 $169.50 $135.00 $150.00 $80.00 $175.00 $125.00
7400-6008 CUT & RESTORE ASPH PAVING1,328SY $120.00 $70.00 $99.00 $108.50 $85.00 $50.00 $55.00 $95.00 $150.00
8400-6012 CUT AND RESTORE PAV (FLEX BASE)3,932SY $50.00 $30.00 $53.00 $45.50 $37.50 $25.00 $30.00 $50.00 $45.00
9432-6001 RIPRAP (CONC)(4 IN)120CY $350.00 $765.00 $380.00 $275.00 $450.00 $400.00 $400.00 $550.00 $500.00
10464-6003 RC PIPE (CL III)(18 IN)9,958LF $45.00 $33.50 $44.00 $32.72 $38.00 $40.00 $38.00 $40.00 $35.00
11464-6005 RC PIPE (CL III)(24 IN)1,516LF $50.00 $48.00 $54.00 $49.18 $70.00 $75.00 $50.00 $58.00 $45.00
12464-6008 RC PIPE (CL III)(36 IN)99LF $100.00 $80.00 $105.00 $112.13 $128.00 $200.00 $90.00 $125.00 $85.00
13467-6363 SET (TY II) (18 IN) (RCP) (6: 1) (P)1,536EA $550.00 $500.00 $500.00 $540.00 $525.00 $675.00 $570.00 $575.00 $525.00
14467-6395 SET (TY II) (24 IN) (RCP) (6: 1) (P)202EA $850.00 $800.00 $825.00 $885.00 $930.00 $850.00 $935.00 $1,000.00 $875.00
15467-6454 SET (TY II) (36 IN) (RCP) (6: 1) (P)4EA $2,640.00 $3,250.00 $3,350.00 $3,875.00 $3,673.00 $12,000.00 $4,000.00 $5,500.00 $3,500.00
16496-6006 REMOV STR (HEADWALL)37EA $1,000.00 $275.00 $600.00 $825.00 $635.00 $750.00 $400.00 $750.00 $250.00
17496-6007 REMOV STR (PIPE)9,359LF $20.00 $10.00 $11.00 $12.50 $7.00 $5.00 $10.00 $10.00 $10.00
18500-6001 MOBILIZATION1LS $291,000.00 $200,000.00 $200,000.00 $179,000.00 $250,000.00 $240,000.00 $200,000.00 $285,000.00 $400,000.00
19502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING15MO $2,500.00 $2,000.00 $5,000.00 $2,200.00 $3,000.00 $1,500.00 $4,000.00 $6,000.00 $5,000.00
20560-6011 MAILBOX INSTALL-S (TWW-POST) TY 41EA $350.00 $350.00 $600.00 $375.00 $735.00 $500.00 $1,000.00 $1,000.00 $500.00
216185-6001 TMA (STATIONARY)1EA $15,000.00 $7,500.00 $23,000.00 $6,500.00 $50,000.00 $12,000.00 $15,000.00 $17,500.00 $25,000.00

Showing the first 8 bidders. The Excel and CSV downloads include all 10.