Filtered by: County: Ward Clear all
| Let date | CCSJ | County / District | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Dec 1, 2026 | 0005-08-107 F 2027(186) | BordenFisherHowardJones+6 moreAbilene | BI 20NBS 208BBU 84JFM 1170+13 more | Seal Coat Resurface Roadway FM 670 to 0.168 Miles East of SH 208 | $12,574,772259 items | Official | ||
| Dec 1, 2026 | 0070-01-056 F 2027(177) | CokeConchoEdwardsGlasscock+7 moreSan Angelo | FM 1223FM 1678FM 1874FM 2406+12 more | Seal Coat FM 388 to SL 306 | $9,464,478254 items | Official | ||
| Jan 6, 2027 | 0069-10-003 BR 2027(290) | HowardAbilene | US 87 | Bridge Maintenance US 87 NBFR to @IH 20 | $1,356,095116 items | Unofficial | ||
| Apr 6, 2027 estimated | 0005-05-119 | HowardAbilene | IH 20 | Safety Improvement Projects Hazard Elimination & Safety at to Exit 165 EB | $778,551 | Planned | ||
| Apr 6, 2027 estimated | 0005-06-131 | HowardAbilene | IH 20 | Safety Improvement Projects Hazard Elimination & Safety at to Exit 188 EB | $778,079 | Planned | ||
| Jun 1, 2027 estimated | 0005-06-129 | HowardAbilene | IH 20 | Rehabilitation of Existing Road Repair Roadway NEAR FM 700 ON N FRT RD to NEAR MIDWAY | $2,500,000 | Planned | ||
| Jul 3, 2027 estimated | 1134-01-022 | HowardAbilene | FM 818 | Intersection & Operational Imprv Donation IH 20 to FM 461 | $6,029,198 | Planned | ||
| Sep 1, 2027 estimated | 1824-01-013 | WardOdessa | FM 1927 | Seal Coat SS 57 to FM 1776 | $954,332 | Planned | ||
| Nov 2, 2027 estimated | 0004-03-055 | WardOdessa | BI 20D | Rehabilitation of Existing Road Rehabilitate Existing Roadway W IH 20 INTERCHANGE to IH 20 E | $26,785,714 | Planned | ||
| Dec 1, 2027 estimated | 0005-05-115 | HowardAbilene | IH 20 | Seal Coat Preventive Maintenance MARTIN CO LINE to 0.404 MILES EAST OF US 87 | $626,974 | Planned | ||
| Dec 1, 2027 estimated | 0375-05-063 | EdwardsSan Angelo | RM 674 | Seal Coat US 377 to KINNEY COUNTY LINE | $1,003,386 | Planned | ||
| Dec 1, 2027 estimated | 0668-01-020 | HowardAbilene | FM 700 | Seal Coat Preventive Maintenance BI 20-G to BU 87-M | $248,804 | Planned | ||
| Dec 1, 2027 estimated | 0668-02-021 | HowardAbilene | FM 700 | Seal Coat Preventive Maintenance BU 87-M to IH 20 | $454,484 | Planned | ||
| Dec 1, 2027 estimated | 0668-04-006 | HowardAbilene | FM 700 | Seal Coat Preventive Maintenance US 87 to SH 350 | $87,747 | Planned | ||
| Dec 1, 2027 estimated | 1156-02-026 | HowardAbilene | FM 821 | Seal Coat Preventive Maintenance GLASSCOCK CO LINE to FM 2183 | $371,668 | Planned | ||
| Dec 1, 2027 estimated | 1653-04-009 | HowardAbilene | FM 461 | Seal Coat Preventive Maintenance US 87 to FM 821 | $170,963 | Planned |
1–16 of 16
Advertised proposals and bid items: TxDOT Official and Unofficial Bid Items (data.texas.gov). Planned projects: TxDOT Projects Info service; their let dates are TxDOT estimates and often slip. Low bidders: TxDOT Bid Tabulations. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.