6482-85-001 PALM TREE TRIM AND REMOVAL
- Let date
- Tuesday, April 15, 2025
- CCSJ
- 6482-85-001
- District
- Pharr
- County
- Hidalgo
- Highway
- IH0002
- Limits
- VARIOUS LOCATIONS to HIDALGO, CAMERON, AND WILLACY COUNTY
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00214871
- Working days
- 480
- DBE goal
- 0%
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $437,000 | ||
| 1 | S FOWLER SERVICES LLC Low bidder | $415,049 | -5.0% | |
| 2 | ArborTrue LLC | $475,800 | +8.9% | +14.6% |
| 3 | SAENZ UTILITY CONTRACTORS, LLC | $501,600 | +14.8% | +20.9% |
| 4 | AUSTIN BARRICADE COMPANY, L.L.C. | $554,230 | +26.8% | +33.5% |
| 5 | GV LANDSCAPE AND CONSTRUCTION LLC | $557,300 | +27.5% | +34.3% |
| 6 | CROSS PLUS CONSTRUCTION, LLC | $694,480 | +58.9% | +67.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 S FOWLER SERVIC… | #2 ArborTrue LLC | #3 SAENZ UTILITY C… | #4 AUSTIN BARRICAD… | #5 GV LANDSCAPE AN… | #6 CROSS PLUS CONS… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7001 | MOBILIZATION | 1 | LS | $30,000.00 | $1.00 | $22,000.00 | $30,000.00 | $75,000.00 | $80,000.00 | $40,000.00 |
| 2 | 505-7001 | TMA (STATIONARY) | 480 | DAY | $150.00 | $0.1000 | $180.00 | $135.00 | $1.00 | $150.00 | $1.00 |
| 3 | 752-7007 | TREE REMOVAL (18" - 24" DIA) | 320 | EA | $250.00 | $500.00 | $670.00 | $315.00 | $500.00 | $390.00 | $450.00 |
| 4 | 7012-7004 | TREE TRIMMING | 2,550 | EA | $100.00 | $100.00 | $60.00 | $120.00 | $125.00 | $110.00 | $200.00 |