| 1 | 100-6002 |
PREPARING ROW | 7.27 | STA |
$2,500.00 |
$4,000.00 |
$4,200.00 |
$2,000.00 |
| 2 | 104-6001 |
REMOVING CONC (PAV) | 600 | SY |
$20.00 |
$40.00 |
$20.00 |
$12.00 |
| 3 | 104-6009 |
REMOVING CONC (RIPRAP) | 75 | SY |
$11.00 |
$15.00 |
$20.00 |
$50.00 |
| 4 | 104-6022 |
REMOVING CONC (CURB AND GUTTER) | 700 | LF |
$6.00 |
$10.00 |
$7.00 |
$12.00 |
| 5 | 105-6037 |
REMOVING STAB BASE AND ASPH PAV(0"-16") | 1,247 | SY |
$5.00 |
$40.00 |
$11.00 |
$20.00 |
| 6 | 110-6001 |
EXCAVATION (ROADWAY) | 1,401.23 | CY |
$11.04 |
$11.00 |
$15.00 |
$22.00 |
| 7 | 110-6002 |
EXCAVATION (CHANNEL) | 90 | CY |
$30.00 |
$80.00 |
$50.00 |
$45.00 |
| 8 | 132-6001 |
EMBANKMENT (FINAL)(ORD COMP)(TY A) | 394 | CY |
$20.00 |
$20.00 |
$45.00 |
$40.00 |
| 9 | 132-6003 |
EMBANKMENT (FINAL)(ORD COMP)(TY B) | 560.61 | CY |
$12.00 |
$20.00 |
$50.00 |
$40.00 |
| 10 | 134-6001 |
BACKFILL (TY A) | 3.77 | STA |
$160.00 |
$4,500.00 |
$2,000.00 |
$1,740.00 |
| 11 | 150-6001 |
BLADING | 7.27 | STA |
$500.00 |
$400.00 |
$600.00 |
$790.00 |
| 12 | 160-6003 |
FURNISHING AND PLACING TOPSOIL (4") | 294 | SY |
$0.7500 |
$6.00 |
$12.00 |
$16.00 |
| 13 | 160-6005 |
FURNISHING AND PLACING TOPSOIL | 150 | CY |
$60.00 |
$50.00 |
$95.00 |
$73.00 |
| 14 | 164-6027 |
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY) | 294 | SY |
$0.4500 |
$3.00 |
$2.50 |
$3.00 |
| 15 | 164-6029 |
CELL FBR MLCH SEED(TEMP)(WARM) | 294 | SY |
$0.4000 |
$3.00 |
$2.50 |
$3.00 |
| 16 | 164-6035 |
DRILL SEEDING (PERM) (RURAL) (CLAY) | 1,790 | SY |
$0.5000 |
$0.6000 |
$0.5000 |
$1.00 |
| 17 | 164-6041 |
DRILL SEEDING (TEMP) (WARM) | 1,790 | SY |
$0.2000 |
$0.6000 |
$0.5000 |
$1.00 |
| 18 | 168-6001 |
VEGETATIVE WATERING | 147.43 | MG |
$35.00 |
$40.00 |
$3.00 |
$20.00 |
| 19 | 169-6006 |
SOIL RETENTION BLANKETS (CL 2) (TY F) | 1,790 | SY |
$2.00 |
$3.20 |
$2.65 |
$3.00 |
| 20 | 247-6060 |
FL BS (CMP IN PLC)(TY E GR 4)(FNAL POS) | 506 | CY |
$85.00 |
$100.00 |
$56.00 |
$65.00 |
| 21 | 247-6236 |
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS) | 356 | CY |
$85.00 |
$170.00 |
$110.00 |
$180.00 |
| 22 | 275-6001 |
CEMENT | 29 | TON |
$200.00 |
$250.00 |
$215.00 |
$300.00 |
| 23 | 275-6046 |
CEMENT TREAT (NEW BASE)(11") | 2,812 | SY |
$5.00 |
$12.00 |
$15.50 |
$3.00 |
| 24 | 310-6009 |
PRIME COAT (MC-30) | 550 | GAL |
$6.00 |
$12.00 |
$9.00 |
$8.00 |
| 25 | 400-6005 |
CEM STABIL BKFL | 185 | CY |
$105.00 |
$150.00 |
$150.00 |
$100.00 |
| 26 | 409-6001 |
PRESTR CONC PIL (16 IN SQ) | 518 | LF |
$160.00 |
$180.00 |
$225.00 |
$200.00 |
| 27 | 416-6002 |
DRILL SHAFT (24 IN) | 336 | LF |
$250.00 |
$300.00 |
$350.00 |
$300.00 |
| 28 | 420-6013 |
CL C CONC (ABUT) | 56.6 | CY |
$950.00 |
$1,300.00 |
$2,500.00 |
$1,500.00 |
| 29 | 422-6007 |
REINF CONC SLAB (SLAB BEAM) | 3,248 | SF |
$27.00 |
$30.00 |
$30.00 |
$60.00 |
| 30 | 425-6009 |
PRESTR CONC SLAB BEAM (4SB12) | 37 | LF |
$200.00 |
$330.00 |
$207.00 |
$535.00 |
| 31 | 425-6010 |
PRESTR CONC SLAB BEAM (5SB12) | 296 | LF |
$250.00 |
$290.00 |
$207.00 |
$375.00 |
| 32 | 425-6011 |
PRESTR CONC SLAB BEAM (4SB15) | 405 | LF |
$220.00 |
$290.00 |
$207.00 |
$375.00 |
| 33 | 432-6008 |
RIPRAP (CONC)(CL B)(RR8&RR9) | 33 | CY |
$450.00 |
$550.00 |
$600.00 |
$857.00 |
| 34 | 432-6033 |
RIPRAP (STONE PROTECTION)(18 IN) | 110 | CY |
$155.00 |
$250.00 |
$230.00 |
$293.00 |
| 35 | 450-6006 |
RAIL (TY T223) | 114 | LF |
$135.00 |
$230.00 |
$150.00 |
$449.00 |
| 36 | 450-6034 |
RAIL (TY C402) | 98 | LF |
$150.00 |
$300.00 |
$230.00 |
$167.00 |
| 37 | 454-6021 |
TYPE A JOINT | 160 | LF |
$80.00 |
$60.00 |
$18.00 |
$413.00 |
| 38 | 464-6003 |
RC PIPE (CL III)(18 IN) | 152 | LF |
$90.00 |
$90.00 |
$160.00 |
$105.00 |
| 39 | 464-6007 |
RC PIPE (CL III)(30 IN) | 96 | LF |
$150.00 |
$180.00 |
$210.00 |
$176.00 |
| 40 | 464-6008 |
RC PIPE (CL III)(36 IN) | 112 | LF |
$200.00 |
$200.00 |
$220.00 |
$260.00 |
| 41 | 465-6029 |
INLET (COMPL)(PCU)(3FT)(NONE) | 1 | EA |
$6,000.00 |
$3,250.00 |
$5,000.00 |
$5,615.00 |
| 42 | 467-6363 |
SET (TY II) (18 IN) (RCP) (6: 1) (P) | 1 | EA |
$1,200.00 |
$1,500.00 |
$1,300.00 |
$1,836.00 |
| 43 | 467-6423 |
SET (TY II) (30 IN) (RCP) (6: 1) (P) | 2 | EA |
$3,000.00 |
$2,500.00 |
$2,100.00 |
$2,897.00 |
| 44 | 467-6454 |
SET (TY II) (36 IN) (RCP) (6: 1) (P) | 1 | EA |
$5,000.00 |
$3,400.00 |
$8,000.00 |
$4,138.00 |
| 45 | 496-6001 |
REMOV STR (BOX CULVERT) | 1 | EA |
$5,500.00 |
$5,000.00 |
$2,000.00 |
$55,250.00 |
| 46 | 496-6005 |
REMOV STR (WINGWALL) | 4 | EA |
$1,500.00 |
$800.00 |
$5,000.00 |
$3,749.00 |
| 47 | 496-6007 |
REMOV STR (PIPE) | 56 | LF |
$30.00 |
$25.00 |
$15.00 |
$23.00 |
| 48 | 496-6009 |
REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 | EA |
$50,000.00 |
$28,000.00 |
$65,000.00 |
$63,500.00 |
| 49 | 500-6001 |
MOBILIZATION | 1 | LS |
$154,000.00 |
$100,000.00 |
$180,000.00 |
$200,000.00 |
| 50 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 | MO |
$4,000.00 |
$1,500.00 |
$4,500.00 |
$5,100.00 |
| 51 | 506-6020 |
CONSTRUCTION EXITS (INSTALL) (TY 1) | 312 | SY |
$30.00 |
$20.00 |
$53.00 |
$30.00 |
| 52 | 506-6024 |
CONSTRUCTION EXITS (REMOVE) | 312 | SY |
$10.00 |
$10.00 |
$26.00 |
$19.00 |
| 53 | 506-6031 |
FRNT END LOADER WORK (ERSN & SEDM CONT) | 60 | HR |
$100.00 |
$100.00 |
$140.00 |
$274.00 |
| 54 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,341 | LF |
$6.00 |
$5.00 |
$4.15 |
$5.00 |
| 55 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,341 | LF |
$2.00 |
$1.50 |
$1.25 |
$1.00 |
| 56 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 581 | LF |
$6.00 |
$6.75 |
$5.50 |
$7.00 |
| 57 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 581 | LF |
$1.00 |
$1.50 |
$1.25 |
$1.00 |
| 58 | 529-6008 |
CONC CURB & GUTTER (TY II) | 700 | LF |
$23.50 |
$30.00 |
$13.50 |
$59.00 |
| 59 | 530-6005 |
DRIVEWAYS (ACP) | 261.1 | SY |
$40.00 |
$100.00 |
$70.00 |
$57.00 |
| 60 | 530-6016 |
DRIVEWAYS (BASE) | 178.1 | SY |
$70.00 |
$70.00 |
$35.00 |
$13.00 |
| 61 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 150 | LF |
$35.00 |
$55.00 |
$43.00 |
$41.00 |
| 62 | 540-6006 |
MTL BEAM GD FEN TRANS (THRIE-BEAM) | 2 | EA |
$2,300.00 |
$2,900.00 |
$2,000.00 |
$1,968.00 |
| 63 | 540-6016 |
DOWNSTREAM ANCHOR TERMINAL SECTION | 1 | EA |
$3,200.00 |
$700.00 |
$1,500.00 |
$1,431.00 |
| 64 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 1 | EA |
$3,400.00 |
$3,200.00 |
$3,500.00 |
$3,133.00 |
| 65 | 545-6006 |
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2) | 6 | EA |
$25,000.00 |
$32,000.00 |
$23,000.00 |
$25,480.00 |
| 66 | 644-6027 |
IN SM RD SN SUP&AM TYS80(1)SA(P) | 11 | EA |
$750.00 |
$800.00 |
$820.00 |
$1,136.00 |
| 67 | 644-6076 |
REMOVE SM RD SN SUP&AM | 8 | EA |
$125.00 |
$200.00 |
$75.00 |
$75.00 |
| 68 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 4 | EA |
$32.68 |
$20.00 |
$13.50 |
$38.00 |
| 69 | 658-6073 |
INSTL OM ASSM (OM-2Y)(WC)GND(BI) | 4 | EA |
$90.00 |
$30.00 |
$37.00 |
$80.00 |
| 70 | 666-6303 |
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | 1,443 | LF |
$3.00 |
$2.50 |
$2.50 |
$2.00 |
| 71 | 666-6315 |
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | 1,443 | LF |
$3.00 |
$2.50 |
$2.50 |
$2.00 |
| 72 | 668-6036 |
PREFAB PAV MRK TY B (W)(BIKE ARROW) | 4 | EA |
$250.00 |
$265.00 |
$300.00 |
$240.00 |
| 73 | 668-6096 |
PREFAB PAV MRK TY C (W)(BIKE SYMBOL) | 4 | EA |
$255.00 |
$265.00 |
$250.00 |
$240.00 |
| 74 | 672-6009 |
REFL PAV MRKR TY II-A-A | 19 | EA |
$8.00 |
$11.00 |
$5.00 |
$10.00 |
| 75 | 678-6001 |
PAV SURF PREP FOR MRK (4") | 1,035 | LF |
$1.00 |
$0.3000 |
$0.5000 |
$0.3000 |
| 76 | 3076-6049 |
D-GR HMA TY-D SAC-A PG76-22 | 458.1 | TON |
$145.00 |
$220.00 |
$220.00 |
$212.00 |
| 77 | 5001-6002 |
GEOGRID BASE REINFORCEMENT (TY II) | 1,164 | SY |
$1.75 |
$3.00 |
$5.00 |
$3.00 |