10-26 Angelina Ditch Cleaning
- Let date
- Wednesday, October 28, 2026
- CCSJ
- 6510-42-001
- District
- Lufkin
- County
- Angelina
- Highway
- US0059
- Limits
- VARIOUS LOCATIONS IN POLK COUNTY to MAINTENANCE SECTION
- Classification
- Routine Maintenance Project · Maintenance
- Project number
- RMC - A00224208
- Working days
- 365
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $385,050 | ||
| 1 | TEXAS DRAINAGE INC. Low bidder | $283,926 | -26.3% | |
| 2 | ROW Contractors LLC | $345,800 | -10.2% | +21.8% |
| 3 | DIGG COMMERCIAL, LLC | $397,530 | +3.2% | +40.0% |
| 4 | GROD CONSTRUCTION LLC | $534,200 | +38.7% | +88.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TEXAS DRAINAGE … | #2 ROW Contractors… | #3 DIGG COMMERCIAL… | #4 GROD CONSTRUCTI… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 164-7033 | BROADCAST SEED (PERM_RURAL_SAND) | 0.5 | AC | $1,400.00 | $0.9900 | $1,500.00 | $9,000.00 | $9,200.00 |
| 2 | 480-7001 | CLEAN EXIST CULVERTS | 50 | EA | $2,000.00 | $225.00 | $400.00 | $1,000.00 | $2,000.00 |
| 3 | 500-7002 | MOBILIZATION (CALLOUT) | 30 | EA | $600.00 | $100.00 | $400.00 | $1.00 | $3,500.00 |
| 4 | 505-7001 | TMA (STATIONARY) | 75 | DAY | $200.00 | $1.00 | $150.00 | $1,200.00 | $300.00 |
| 5 | 506-7039 | TEMP SEDMT CONT FENCE (INSTALL) | 300 | LF | $3.00 | $1.00 | $5.00 | $8.00 | $5.00 |
| 6 | 506-7041 | TEMP SEDMT CONT FENCE (REMOVE) | 300 | LF | $1.50 | $1.00 | $1.00 | $2.00 | $2.00 |
| 7 | 760-7001 | DITCH CLEANING AND RESHAPING (FOOT) | 100,000 | LF | $2.50 | $2.69 | $3.00 | $2.50 | $3.00 |