MOWING HIGHWAY RIGHT OF WAY
- Let date
- Friday, October 6, 2023
- CCSJ
- 6451-53-001
- District
- Lubbock
- County
- Lubbock
- Highway
- IH 27
- Limits
- VARIOUS to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 645153001
- Working days
- 730
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $394,800 | ||
| 1 | MARLANE CONSTRUCTION, LLC Low bidder | $372,420 | -5.7% | |
| 2 | ICOS MANAGEMENT, LLC | $392,955 | -0.5% | +5.5% |
| 3 | GORMAN OUTDOOR, INC. | $625,086 | +58.3% | +67.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 MARLANE CONSTRU… | #2 ICOS MANAGEMENT… | #3 GORMAN OUTDOOR,… |
|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 6 | EA | $1,000.00 | $1,000.00 | $2,500.00 | $1.00 |
| 2 | 730-6002 | FULL - WIDTH MOWING | 7,476 | AC | $50.00 | $45.00 | $48.75 | $80.00 |
| 3 | 6185-6005 | TMA (MOBILE OPERATION) | 30 | DAY | $500.00 | $1,000.00 | $450.00 | $900.00 |