Rehabilitation of Existing Road
OfficialBid items 13
Notice Averages Review estimate Draft from history Excel HCSS HeavyBid CSV| Seq | Bid code | Description | Quantity | Unit |
|---|---|---|---|---|
| 2 | ||||
| 2 | ||||
| 1 | 351-7003 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")FLEXIBLE PAVEMENT STRUCTURE REPAIR | 123 | SY |
| 2 | 361-7005 | FULL - DEPTH REPAIR CRCP (10")FULL-DEPTH REPAIR OF CONCRETE PAVEMENT | 2,919.602 | CY |
| 3 | 400-7010 | CEM STABIL BKFLEXCAVATION AND BACKFILL FOR STRUCTURES | 50 | CY |
| 4 | 500-7001 | MOBILIZATION | 1 | LS |
| 5 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLINGBARRICADES, SIGNS, AND TRAFFIC HANDLING | 10 | MO |
| 6 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 600 | DAY |
| 7 | 505-7001 | TMA (STATIONARY)TRUCK-MOUNTED ATTENUATOR (TMA) AND TRAILER ATTENUATOR (TA) | 590 | DAY |
| 8 | 506-7035 | SANDBAGS FOR EROSION CONTROLTEMPORARY EROSION, SEDIMENTATION, AND ENVIRONMENTAL CONTROLS | 65 | EA |
| 9 | 506-7045 | BIODEG EROSN CONT LOGS (INSTL) (18")TEMPORARY EROSION, SEDIMENTATION, AND ENVIRONMENTAL CONTROLS | 100 | LF |
| 10 | 506-7046 | BIODEG EROSN CONT LOGS (REMOVE)TEMPORARY EROSION, SEDIMENTATION, AND ENVIRONMENTAL CONTROLS | 100 | LF |
| 11 | 7014-7001 | CURB INLET SEDIMENT PROTECTIONCURB INLET SEDIMENT CONTROL DEVICE | 75 | LF |
Pre-bid questions 5
Please post the Contract Time Determination (CTD) Schedule Nov 12, 2026
Q: Can you please post the Contract Time Determination (CTD) Schedule?
A: See the uploaded CTD Schedule. · Michael Boyd
CONCRETE PAYMENT Nov 13, 2026
Q: Per the updated specification, concrete placement should be quantified and bid by the cubic yard (CY) rather than the square yard (SY) to accurately account for variable section depths. TxDOT will revise these items to adhere to the governing specification, correct?
-In previous lettings, bidding similar items by the square yard has led to post-award negotiations and change orders to reconcile actual material quantities. On a project of this scale and given current ready-mix material costs, pricing by volume is essential to ensure transparent, equitable bidding across ALL contractors and to guarantee payment for ALL verified cubic yards placed, correct?
A: Addendum 2 will be processed to revise plan sheets and estimate to reflect quantities by the Cubic Yard (CY) for item 360. · Joe Villalobos
item 360 Nov 20, 2026
Q: Based on the strength testing requirements under Item 360, overnight lane closures will be permitted, correct?
A: Overnight lane closures are expected, but the contractor is to provide HES concrete which attains a minimum average compressive strength of 3,200 psi at 24 hours or when opening a repaired area to traffic in less than 24 hours, design the Class HES concrete to attain a minimum average compressive strength of 1,800 psi within 8 hours. The Engineer will perform job control testing and testing for opening to all traffic. · Joe Villalobos
item 360 Nov 23, 2026
Q: ARE THERE REMOVALS THAT HAVE TO BE ACCOMPLISHED IN LESS THAN 24 HOURS? IF SO, HOW MANY AND WHERE?
IT APPEARS YOU ARE ASKING FOR 2 DIFFERENT TYPES OF CONCRETE: A HES AND A RAPID SET (OR A VERY FAST HES)
A: Daily removals are expected and concrete is to be placed within 1 day/24 hours. Ramp locations with larger areas of removal and replacement may necessitate multi day removal and placement. Follow all TCP and public notification requirements for extended closures. Provide HES Concrete. · Joe Villalobos
item 360 Nov 24, 2026
Q: Please clarify the application of the "1800 PSI in 8 hours" concrete requirement. Is this specification intended for locations where TxDOT requires lane closures to be removed and reopened to traffic within the same day? If so, please identify the specific locations and total quantity of areas where this requirement applies.
A: This a requirement for all locations. It is expected to have locations opened as soon as possible to traffic. 1800psi within 8 hours or 3200psi within 24 hours are the two, early opening to traffic specification requirements to be met. · Joe Villalobos
From TxDOT's Pre-bid Question and Answer data. Answers become part of the proposal; check the official packet before bidding.