Bid tab 0367-06-065

Let Dec 2, 2025 · Houston · Galveston Sign up free

‹ Dec 2025 results

SH 87, Galv Ferry Landing Improvements

Let date
Tuesday, December 2, 2025
CCSJ
0367-06-065
District
Houston
County
Galveston
Highway
SH 87
Limits
At Galveston Ferry Landing to .
Classification
Ferry Boat · Construction
Project number
F 2026(358)
Working days
1082
DBE goal
0%

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$53,000,000
1 TEXAS GULF CONSTRUCTION COMPANY, INC. Low bidder $53,235,450 +0.4%
2 RAGLE CONSTRUCTION, INC. $68,933,000 +30.1% +29.5%
3 CALLAN MARINE LTD $97,492,443 +83.9% +83.1%

Bid tab: unit prices 1 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 TEXAS GULF CONS…#2 RAGLE CONSTRUCT…#3 CALLAN MARINE L…
17052-7001 FERRY LANDING AND FACILITIES UPGRADE1LS $53,000,000.00 $53,235,450.00 $68,933,000.00 $97,492,443.00