Rigid Pavement Repair -EAO
- Let date
- Thursday, May 1, 2025
- CCSJ
- 6478-66-001
- District
- El Paso
- County
- El Paso
- Highway
- IH0010
- Limits
- VARIOUS LOCATIONS to VARIOUS LOCATIONS
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00213435
- Working days
- 365
- DBE goal
- 0%
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,381,000 | ||
| 1 | SYNERGY PROJECT CONTRACTORS, INC. Low bidder | $1,271,955 | -7.9% | |
| 2 | DAN WILLIAMS COMPANY | $1,975,000 | +43.0% | +55.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SYNERGY PROJECT… | #2 DAN WILLIAMS CO… |
|---|---|---|---|---|---|---|---|
| 1 | 361-7044 | FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 550 | CY | $2,000.00 | $2,052.00 | $2,800.00 |
| 2 | 429-7004 | CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 | SF | $240.00 | $51.30 | $200.00 |
| 3 | 429-7006 | CONC STR REPR(RAPID DECK REP(FULL DPT)) | 200 | SF | $430.00 | $153.90 | $300.00 |
| 4 | 500-7001 | MOBILIZATION | 1 | LS | $12,000.00 | $11,400.00 | $197,000.00 |
| 5 | 500-7003 | MOBILIZATION (CALLOUT 1) | 3 | EA | $3,000.00 | $2,280.00 | $15,000.00 |
| 6 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 10 | DAY | $350.00 | $171.00 | $200.00 |
| 7 | 505-7001 | TMA (STATIONARY) | 250 | DAY | $400.00 | $267.90 | $200.00 |
| 8 | 720-7001 | SPALLING REPAIR (HYDRAULIC CEMENT) | 100 | CF | $225.00 | $153.90 | $410.00 |