CCSJ 0337-05-043

Bryan · Milam Sign up free

‹ All TxDOT jobs My Jobs

Bridge Replacement

Planned

AT LITTLE RIVER to .

Estimated let
Tuesday, February 2, 2027
District
Bryan
County
Milam
Highway
FM 486
Type of work
Bridge Replacement
Let type
Statewide Let
Length
0 mi
MPO
NA
Stage
PS&E
Project ID
A00122349
Added
Nov 25, 2026

Pre-bid questions 25

Remove Str (CONC) Bid Item# 34 Apr 18, 2024

Q: What and where is the concrete removal? It's not shown in the plans.

A: The Quantity for REMOV STR (CONC) was included on the Roadway Quantity Summary in error. Contractor is directed to bid on all items in the Estimate. Any overruns or underruns in the plans will be addressed as outlined in the Spec Book under Item 4, "Scope of Work". · Bradley Peikert

Cross sections Apr 22, 2024

Q: Can you post the cross sections in PDF format?

A: Yes. See attachment. · Bradley Peikert

time determination schedule Apr 22, 2024

Q: Can you post the time determination schedule?

A: Yes. See attachment. For Contractor's Information Only. · Bradley Peikert

Dates listed in traffic control plan Apr 23, 2024

Q: Can you explain the dates listed in red on traffic control pages 15 and 17?

A: Those are estimated ROW clearance dates for the numbered parcels. See 000-1558 Special Provision "IMPORTANT NOTICE TO CONTRACTORS". · Bradley Peikert

Dates listed in traffic control plan Apr 23, 2024

Q: just checked the proposal and I don't see the 000-1558 special provision. That page did not print in the proposal. It shows an error on the page following SP 000-1243. Please provide this page if possible.

A: Thank you for bringing this error to our attention. We are investigating the issue and are working on a response. · Bradley Peikert

Lime treat existing material 10" Apr 23, 2024

Q: This item will actually be lime treating the existing material and whatever material is added to the existing elevations to achieve the new sub grade. The basis of estimate show this as Lime 10" subgrade. Is this correct?

A: Yes. · Bradley Peikert

Cement treat (MX EXT MTL/NW BASE) (OC) 10" Apr 23, 2024

Q: Is the cement treatment 10" item a possible substitute (either or) for the lime treatment 10" item?

A: No. It is not a substitute. It is in addition to the lime treatment. · Bradley Peikert

Cement treat (MX EXT MTL/NW BASE) (OC) 10" Apr 23, 2024

Q: This is similar to the lime item in that the bid item seems to reference a different process than the basis of estimate. The typical shows no cement treat of the new base and the basis of estimate states that it is Cement (10" Subgrade) (2%) Can you clarify?

A: Typical Section is incorrect. Detail A does not reference cement treatment, but it should. Both treatments are required. · Bradley Peikert

FD (MOD) Apr 23, 2024

Q: I found this standard sheet Page 71 as referenced in the table of contents as specifically identified as being applicable to this project. I find no other mention of this particular modification anywhere else in the plans. Is there a modified foundation in either of these bridges? If so where is it located.

A: All interior bent foundations are modified by FD(MOD) sheets. There are only changes to Sheet 70: FD(MOD) Sheet 1 of 2. Sheet 71: FD(MOD) Sheet 2 of 2 remains unchanged and was sealed for consistency. · Bradley Peikert

FD (MOD) Apr 29, 2024

Q: Per the EPIC sheets, Archeological Surveys for Little River and Little River Slough need to be
completed before work can begin. Additionally, the Fresh Water Mussel Survey for Little River
Slough needs to be completed before work can begin. Have these surveys been completed?

A: The archeological surveys for Little River and Little River slough have not been completed. The Fresh Water Mussel survey for Little River Slough has not been completed. All surveys will be completed post-letting, before work begins. · Bradley Peikert

Lead abatement. Apr 29, 2024

Q: Has a contractor been secured to perform the lead abatement required by general note item 496 Removing Structures?

A: Yes. TxDOT has a contractor available. The awarded contractor will need to coordinate with them post-award with demolition details to scope the abatement properly. · Bradley Peikert

508 7001 Construct Detour - typical section Sep 11, 2024

Q: Please indicate where the typical section for the detour paving can be found. If this is not in the plans, please provide the typical section.

A: Detour typical section is not included in the plans. Typical section will consist of 8" HMA (D-GR HMA TY-B PG64-22). · Bradley Peikert

530 7010 Driveways (ACP) Sep 11, 2024

Q: Where is the typical section for the ACP driveways shown in the plans? If it is not in the plans please provide the typical section information for the ACP driveways.

A: Typical section for driveways is not shown in the plans. That item is in error. It should be 530 7015 DRIVEWAYS (BASE). The typical section should be 8" Flex Base (FL BS (CMP IN PLACE)(TY A GR 1-2)(8")). · Bradley Peikert

Detour Structure section Sep 13, 2024

Q: What is the detour asphalt section. Its not shown in the planes

A: Detour typical section is 8" of HMA (D-GR HMA TY-B PG64-22). · Bradley Peikert

Updated Bid Quantities Sep 13, 2024

Q: The bid quantities have changed from when this job was originally scheduled to let in May, however plans are still reflective of old quantities. Will there be a revised set of plans issued reflecting changes?

A: Thank you for bringing this to our attention. We are working to address the issue. · Bradley Peikert

time determination schedule Sep 13, 2024

Q: The time determination schedule provided appears to be for the project as it was to be let in May. Since then, this project has broken each bridge into 2 major phases, with each bridge constructed separately. Also, contract time has gone from 300 working days/19 months to 454 working days/29 months. Is there an updated time determination schedule?

A: See attached for updated Construction Schedule. · Bradley Peikert

new cross sections Sep 23, 2024

Q: Can we get a copy of the new cross sections for the project?

A: Yes. See attached. · Bradley Peikert

time determination schedule Sep 23, 2024

Q: Can we get the new time determination schedule?

A: Yes. See attached. · Bradley Peikert

Pavement structure for Detours Sep 23, 2024

Q: What is the pavement structure for the Detours?

A: Previously answered. See Form ID FM00000045266. · Bradley Peikert

Pavement structure for Detours Sep 23, 2024

Q: Does the temporary subgrade require any treatment?

A: No, the temporary subgrade will not require treatment. · Bradley Peikert

Pavement structure for Detours Sep 23, 2024

Q: Can the subgrade material be incorporated into the slope when removing the detours?

A: Yes, that is acceptable. · Bradley Peikert

excavation and embankment Sep 23, 2024

Q: If it is subsidiary to the detour item, do you have an estimated quantity?

A: No.. Estimated embankment quantity for detour was not calculated or tabulated. · Bradley Peikert

excavation and embankment Sep 23, 2024

Q: Was the detour embankment calculated into the bid items or is it subsidiary to the detour item?

A: Detour embankment quantity should be subsidiary to the detour item. · Bradley Peikert

Updated Bid Quantities Sep 23, 2024

Q: Any update on this?

A: We are still working on the issue. · Bradley Peikert

Temporary Spl Shoring Sep 29, 2024

Q: Can a profile sheet for the temporary special shoring be provided?

A: No temporary special shoring profile is available. Please note that this project letting has been moved from October 2024 to September 2026. · Bradley Peikert

From TxDOT's Pre-bid Question and Answer data. Answers become part of the proposal; check the official packet before bidding.