BMT_IH0010_3 (2022 HSIP) SAFETY LIGHTING
- Let date
- Wednesday, October 8, 2025
- CCSJ
- 0508-02-133
- District
- Beaumont
- County
- Chambers
- Highway
- IH 10
- Limits
- 0.37 MI W OF FM 563 to 0.36 MI E OF FM 563
- Classification
- Safety Improvement Projects · Construction
- Project number
- STP 2026(035)VRU
- Working days
- 36
- DBE goal
- 0%
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $1,112,605 | | |
| 1 |
ALLSTATE SIGNAL & CONSTRUCTION, LLC Low bidder |
$1,064,705 |
-4.3% |
|
| 2 |
DECO CONTRACTORS, INC. |
$1,074,363 |
-3.4% |
+0.9% |
| 3 |
THIRD COAST SERVICES LLC |
$1,082,631 |
-2.7% |
+1.7% |
| 4 |
STRUCTURAL INTEGRITY GROUP LLC |
$1,091,434 |
-1.9% |
+2.5% |
| 5 |
CREACOM, INC. |
$1,138,381 |
+2.3% |
+6.9% |
| 6 |
TRAF-TEX, INC. |
$1,197,284 |
+7.6% |
+12.5% |
| 7 |
FLORIDA TRAFFIC CONTROL DEVICES, INC. |
$1,231,450 |
+10.7% |
+15.7% |
| 8 |
LIGHT IT UP ELECTRIC |
$1,275,151 |
+14.6% |
+19.8% |
| 9 |
SICE, INC. |
$1,282,743 |
+15.3% |
+20.5% |
| 10 |
SELECT MAINTENANCE, L.L.C. |
$1,429,595 |
+28.5% |
+34.3% |
Bid tab: unit prices 23 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 ALLSTATE SIGNAL… | #2 DECO CONTRACTOR… | #3 THIRD COAST SER… | #4 STRUCTURAL INTE… | #5 CREACOM, INC. | #6 TRAF-TEX, INC. | #7 FLORIDA TRAFFIC… | #8 LIGHT IT UP ELE… |
| 1 | 134-7002 |
BACKFILL (TY B) | 10.65 | STA |
$200.00 |
$355.00 |
$350.00 |
$211.83 |
$63.40 |
$402.12 |
$173.00 |
$822.00 |
$100.00 |
| 2 | 416-7037 |
DRILL SHAFT (HIGH MAST POLE) (60 IN) | 270 | LF |
$850.00 |
$748.89 |
$695.00 |
$640.26 |
$761.01 |
$633.36 |
$981.35 |
$951.00 |
$850.00 |
| 3 | 432-7001 |
RIPRAP (CONC)(4 IN) | 16 | CY |
$600.00 |
$450.60 |
$800.00 |
$1,481.76 |
$645.05 |
$1,429.95 |
$1,985.00 |
$1,057.00 |
$1,300.00 |
| 4 | 432-7013 |
RIPRAP (MOW STRIP)(4 IN) | 59 | CY |
$640.00 |
$501.83 |
$975.00 |
$732.00 |
$585.30 |
$1,206.15 |
$615.00 |
$1,175.00 |
$1,700.00 |
| 5 | 500-7001 |
MOBILIZATION | 1 | LS |
$110,230.00 |
$86,500.00 |
$100,000.00 |
$108,263.14 |
$96,258.70 |
$79,686.67 |
$96,478.00 |
$100,000.00 |
$105,000.00 |
| 6 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 | MO |
$4,000.00 |
$6,657.00 |
$2,250.00 |
$18,879.32 |
$11,359.39 |
$3,163.16 |
$1,242.00 |
$7,230.00 |
$6,000.00 |
| 7 | 505-7001 |
TMA (STATIONARY) | 36 | DAY |
$200.00 |
$200.00 |
$250.00 |
$413.63 |
$200.00 |
$455.80 |
$410.00 |
$164.00 |
$300.00 |
| 8 | 506-7039 |
TEMP SEDMT CONT FENCE (INSTALL) | 150 | LF |
$4.00 |
$5.00 |
$11.00 |
$6.71 |
$1.00 |
$4.90 |
$6.60 |
$18.50 |
$10.00 |
| 9 | 506-7041 |
TEMP SEDMT CONT FENCE (REMOVE) | 150 | LF |
$4.00 |
$2.00 |
$1.00 |
$7.52 |
$0.1000 |
$2.01 |
$1.00 |
$8.25 |
$4.00 |
| 10 | 506-7044 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 58 | LF |
$7.00 |
$5.75 |
$7.00 |
$27.57 |
$1.00 |
$17.06 |
$12.30 |
$51.00 |
$15.00 |
| 11 | 506-7046 |
BIODEG EROSN CONT LOGS (REMOVE) | 58 | LF |
$3.00 |
$2.00 |
$1.00 |
$19.45 |
$0.1000 |
$17.35 |
$5.05 |
$36.00 |
$5.00 |
| 12 | 540-7001 |
MTL W-BEAM GD FEN (TIM POST) | 825 | LF |
$28.00 |
$23.10 |
$28.00 |
$28.15 |
$21.00 |
$36.80 |
$25.55 |
$24.00 |
$35.00 |
| 13 | 540-7015 |
DOWNSTREAM ANCHOR TERMINAL SECTION | 4 | EA |
$1,700.00 |
$1,738.00 |
$1,900.00 |
$1,447.11 |
$1,580.00 |
$1,524.23 |
$2,375.00 |
$1,850.00 |
$2,000.00 |
| 14 | 544-7001 |
GUARDRAIL END TREATMENT (INSTALL) | 4 | EA |
$3,320.00 |
$3,190.00 |
$3,500.00 |
$3,265.84 |
$2,900.00 |
$4,357.83 |
$3,800.00 |
$3,400.00 |
$3,800.00 |
| 15 | 613-7006 |
HI MST IL POLE (150 FT)(100 MPH) | 6 | EA |
$57,000.00 |
$59,715.50 |
$58,250.00 |
$53,184.74 |
$59,297.70 |
$64,185.74 |
$58,188.00 |
$56,200.00 |
$67,150.00 |
| 16 | 614-7002 |
LED HI MST IL ASM (6 FIXT) (TY A) | 6 | EA |
$37,000.00 |
$35,520.00 |
$37,750.00 |
$36,753.99 |
$35,747.00 |
$41,459.18 |
$40,475.00 |
$44,500.00 |
$38,000.00 |
| 17 | 618-7054 |
CONDT (PVC) (SCH 80) (2") | 2,667 | LF |
$15.00 |
$12.90 |
$8.95 |
$7.32 |
$15.74 |
$7.79 |
$13.70 |
$14.00 |
$14.00 |
| 18 | 618-7055 |
CONDT (PVC) (SCH 80) (2") (BORE) | 315 | LF |
$15.20 |
$15.90 |
$12.00 |
$9.96 |
$27.95 |
$16.84 |
$28.00 |
$17.00 |
$32.00 |
| 19 | 620-7009 |
ELEC CONDR (NO.6) BARE | 2,982 | LF |
$1.80 |
$2.36 |
$1.85 |
$1.51 |
$1.76 |
$1.37 |
$2.50 |
$1.70 |
$2.00 |
| 20 | 620-7010 |
ELEC CONDR (NO.6) INSULATED | 5,964 | LF |
$2.00 |
$2.66 |
$2.15 |
$1.73 |
$2.23 |
$1.72 |
$2.65 |
$2.20 |
$2.25 |
| 21 | 624-7002 |
GROUND BOX TY A (122311)W/APRON | 13 | EA |
$1,600.00 |
$1,145.00 |
$952.00 |
$728.04 |
$1,272.61 |
$929.73 |
$1,159.00 |
$1,445.00 |
$1,550.00 |
| 22 | 628-7091 |
ELC SRV TY A 240/480 100(SS)SS(E)SP(O) | 2 | EA |
$6,000.00 |
$9,380.00 |
$7,500.00 |
$13,428.44 |
$5,369.35 |
$9,824.22 |
$11,640.00 |
$8,872.00 |
$7,800.00 |
| 23 | 658-7036 |
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 12 | EA |
$28.00 |
$49.50 |
$48.45 |
$37.16 |
$45.00 |
$42.97 |
$50.00 |
$52.00 |
$75.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.