0Bids to
0Wins (low bidder)
0.0%Win rate
$0Total won
Subcontracts on active jobs 10
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 0049-09-102Let May 1, 2025 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 1.03% | $46,040 |
| 0027-10-077Let Oct 2, 2024 | MC2 CIVIL, LLC | HarrisHouston | MISCELLANEOUS CONSTRUCTION | 0.22% | $84,641 |
| 0271-07-326Let Aug 1, 2024 | WEBBER, LLC | HarrisHouston | MISCELLANEOUS CONSTRUCTION | 0.03% | $123,956 |
| 0005-14-094Let Mar 6, 2024 | SUNDT CONSTRUCTION, INC. | MidlandOdessa | WIDEN FREEWAY | 0.27% | $446,446 |
| 0320-06-008Let Feb 2, 2024 | JAMES CONSTRUCTION GROUP, LLC | BellWaco | WIDEN NON-FREEWAY | 0.32% | $177,081 |
| 0005-13-064Let Nov 2, 2023 | SUNDT CONSTRUCTION, INC. | EctorOdessa | WIDEN FREEWAY | 0.3% | $725,367 |
| 0389-06-088Let May 5, 2023 | JAMES CONSTRUCTION GROUP, LLC | GalvestonHouston | WIDEN FREEWAY | 0.1% | $200,589 |
| 0675-07-097Let Sep 2, 2021 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | WalkerBryan | WIDEN FREEWAY | 0.1% | $229,969 |
| 0523-09-009Let Aug 5, 2021 | JAMES CONSTRUCTION GROUP, LLC | MontgomeryHouston | WIDEN NON-FREEWAY | 0.42% | $206,562 |
| 2093-01-010Let Jun 4, 2020 | JAMES CONSTRUCTION GROUP, LLC | Fort BendHouston | WIDEN NON-FREEWAY | 0.56% | $270,961 |