2BidsJun 14, 2023 to Nov 2, 2023
2Wins (low bidder)
100.0%Win rate
$488,253Total won
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Nov 2, 2023 | 0910-16-182 | INSTALL ILLUMINATIONSmith · Tyler | 1 of 6 | $232,606 | $232,606 | Won |
| Jun 14, 2023 | 6443-36-001 | ILLUMINATION MAINTENANCEAngelina · Lufkin | 1 of 1 | $255,647 | $255,647 | Won |
Subcontracts on active jobs 6
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 0046-03-038Let Aug 1, 2024 | DRAKE COMPANIES LLC | BowieAtlanta | REHABILITATION OF EXISTING ROAD | 0% | $0 |
| 0275-01-244Let Jun 6, 2024 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | PotterAmarillo | HAZARD ELIMINATION & SAFETY | 13.99% | $1,609,353 |
| 0203-05-039Let Mar 5, 2024 | LAMAR COMPANIES LLC | WoodTyler | INTERCHANGE (NEW OR RECONSTRUCTED) | 0.74% | $289,049 |
| 0520-04-026Let May 4, 2023 | LONGVIEW BRIDGE AND ROAD, LTD. | MarionAtlanta | BRIDGE REPLACEMENT | 1.51% | $830,521 |
| 0910-07-072Let Mar 3, 2022 | RAGLE CONSTRUCTION, INC. | GreggTyler | BRIDGE REPLACEMENT | 1.55% | $159,152 |
| 0176-01-081Let Jul 9, 2019 | LONGVIEW BRIDGE AND ROAD, LTD. | NacogdochesLufkin | INTERCHANGE (NEW OR RECONSTRUCTED) | 0.32% | $307,221 |