$107.84Avg low bid / TON
$109.60Avg of all bids
$100.07Avg engineer's estimate
5Jobs · 14,900 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 1,500 | $118.40 | $122.05 |
| 2023 | 1 | 200 | $131.40 | $131.40 |
| 2022 | 2 | 6,200 | $121.38 | $121.35 |
| 2021 | 1 | 7,000 | $92.91 | $92.91 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 5, 2024 | 6408-87-001 | BastropAustin | 1,500 TON | $118.40 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Mar 14, 2023 | 6436-72-001 | RunnelsSan Angelo | 200 TON | $131.40 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Sep 8, 2022 | 6404-66-001 | BastropAustin | 6,000 TON | $121.52 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 26, 2022 | 6401-60-001 | Tom GreenSan Angelo | 200 TON | $117.20 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Oct 8, 2021 | 6383-62-001 | BastropAustin | 7,000 TON | $92.91 | VULCAN CONSTRUCTION MATERIALS, LLC |