$28.39Avg low bid / TON
$28.92Avg of all bids
$25.40Avg engineer's estimate
5Jobs · 10,000 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 2,000 | $34.10 | $34.37 |
| 2023 | 1 | 2,000 | $32.10 | $33.31 |
| 2022 | 1 | 2,000 | $29.60 | $29.00 |
| 2021 | 1 | 2,000 | $23.00 | $25.96 |
| 2020 | 1 | 2,000 | $23.16 | $23.46 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Apr 4, 2024 | 6463-28-001 | LamarParis | 2,000 TON | $34.10 | RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
| May 4, 2023 | 6435-78-001 | LamarParis | 2,000 TON | $32.10 | RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
| May 4, 2022 | 6400-41-001 | LamarParis | 2,000 TON | $29.60 | RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
| Apr 7, 2021 | 6377-91-001 | LamarParis | 2,000 TON | $23.00 | RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
| May 7, 2020 | 6361-29-001 | LamarParis | 2,000 TON | $23.16 | RK HALL, LLC |