$133.56Avg low bid / TON
$139.62Avg of all bids
$130.97Avg engineer's estimate
23Jobs · 10,265 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 2 | 700 | $168.57 | $175.88 |
| 2023 | 5 | 1,200 | $160.17 | $164.14 |
| 2022 | 5 | 6,465 | $129.91 | $136.18 |
| 2021 | 8 | 1,600 | $117.81 | $127.36 |
| 2020 | 3 | 300 | $108.00 | $121.20 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 5, 2024 | 6377-06-001 | RandallAmarillo | 200 TON | $170.00 | RK HALL, LLC |
| Mar 5, 2024 | 6462-85-001 | HartleyAmarillo | 500 TON | $168.00 | BIG CREEK SAND & GRAVEL, INC. |
| Jun 27, 2023 | 6397-78-001 | ArmstrongAmarillo | 200 TON | $164.50 | RK HALL, LLC |
| Apr 26, 2023 | 6397-74-001 | HansfordAmarillo | 150 TON | $160.00 | BIG CREEK SAND & GRAVEL, INC. |
| Apr 26, 2023 | 6397-75-001 | HemphillAmarillo | 150 TON | $160.00 | BIG CREEK SAND & GRAVEL, INC. |
| Mar 14, 2023 | 6397-72-001 | RandallAmarillo | 200 TON | $144.00 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Jan 6, 2023 | 6397-69-001 | MooreAmarillo | 500 TON | $165.00 | RK HALL, LLC |
| Jun 29, 2022 | 6407-13-001 | RandallAmarillo | 200 TON | $160.00 | RK HALL, LLC |
| Feb 10, 2022 | 6395-93-001 | Deaf SmithAmarillo | 200 TON | $127.45 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Feb 10, 2022 | 6396-04-001 | MooreAmarillo | 200 TON | $159.00 | RK HALL, LLC |
| Feb 10, 2022 | 6396-05-001 | GrayAmarillo | 200 TON | $127.45 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Feb 4, 2022 | 6382-48-001 | MooreAmarillo | 5,665 TON | $128.00 | BIG CREEK SAND & GRAVEL, INC. |
| Aug 17, 2021 | 6382-37-001 | OldhamAmarillo | 200 TON | $118.00 | RK HALL, LLC |
| Aug 17, 2021 | 6382-38-001 | ArmstrongAmarillo | 200 TON | $118.00 | RK HALL, LLC |
| Aug 17, 2021 | 6382-36-001 | RandallAmarillo | 200 TON | $118.00 | RK HALL, LLC |
| Jul 20, 2021 | 6382-24-001 | DallamAmarillo | 200 TON | $113.05 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Jul 20, 2021 | 6382-25-001 | DallamAmarillo | 200 TON | $113.05 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Mar 11, 2021 | 6375-15-001 | HutchinsonAmarillo | 200 TON | $111.90 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Mar 11, 2021 | 6375-16-001 | Ochiltree | 200 TON | $137.50 | BIG CREEK SAND & GRAVEL, INC. |
| Mar 11, 2021 | 6375-14-001 | CarsonAmarillo | 200 TON | $113.00 | RK HALL, LLC |
| Aug 24, 2020 | 6366-87-001 | PotterAmarillo | 100 TON | $108.00 | RK HALL, LLC |
| Aug 24, 2020 | 6366-88-001 | PotterAmarillo | 100 TON | $108.00 | RK HALL, LLC |
| Aug 24, 2020 | 6366-89-001 | ArmstrongAmarillo | 100 TON | $108.00 | RK HALL, LLC |