‹ All bid codes
$583.90Avg low bid / TON
$609.98Avg of all bids
$603.83Avg engineer's estimate
11Jobs · 530 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
| 2024 | 3 | 150 | $600.47 | $621.42 |
| 2023 | 3 | 150 | $608.51 | $643.80 |
| 2022 | 3 | 130 | $629.84 | $663.68 |
| 2021 | 2 | 100 | $462.45 | $508.45 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
| Apr 15, 2024 | 6461-40-001 |
VictoriaYoakum | 50 TON |
$587.50 | WRIGHT ASPHALT PRODUCTS COMPANY LLC |
| Mar 6, 2024 | 6461-35-001 |
FayetteYoakum | 50 TON |
$611.00 | WRIGHT ASPHALT PRODUCTS COMPANY LLC |
| Feb 1, 2024 | 6461-12-001 |
WhartonYoakum | 50 TON |
$602.90 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Apr 5, 2023 | 6433-26-001 |
VictoriaYoakum | 50 TON |
$626.75 | ERGON ASPHALT & EMULSIONS, INC. |
| Mar 8, 2023 | 6433-08-001 |
FayetteYoakum | 50 TON |
$568.50 | WRIGHT ASPHALT PRODUCTS COMPANY LLC |
| Feb 2, 2023 | 6430-69-001 |
WhartonYoakum | 50 TON |
$630.28 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Apr 26, 2022 | 6399-51-001 |
VictoriaYoakum | 50 TON |
$638.02 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Apr 5, 2022 | 6380-86-001 |
WhartonYoakum | 40 TON |
$620.44 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Mar 29, 2022 | 6398-20-001 |
FayetteYoakum | 40 TON |
$629.00 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Jun 9, 2021 | 6380-85-001 |
VictoriaYoakum | 50 TON |
$441.63 | MARTIN RESOURCE MANAGEMENT CORPORATION |
| Jun 7, 2021 | 6380-84-001 |
FayetteYoakum | 50 TON |
$483.26 | CLEVELAND ASPHALT PRODUCTS, INC. |