$4.01Avg low bid / GAL
$4.01Avg of all bids
$4.34Avg engineer's estimate
5Jobs · 25,000 GAL
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 500 | $3.46 | $3.46 |
| 2025 | 3 | 24,000 | $4.03 | $4.03 |
| 2024 | 1 | 500 | $3.71 | $3.71 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 10, 2026 | 6504-71-001 | WoodTyler | 500 GAL | $3.46 | ERGON ASPHALT & EMULSIONS, INC. |
| Oct 7, 2025 | 6484-70-001 | BrewsterEl Paso | 18,000 GAL | $4.18 | ERGON ASPHALT & EMULSIONS, INC. |
| Feb 11, 2025 | 6476-16-001 | HendersonTyler | 5,000 GAL | $3.55 | ERGON ASPHALT & EMULSIONS, INC. |
| Feb 11, 2025 | 6476-12-001 | GreggTyler | 1,000 GAL | $3.66 | ERGON ASPHALT & EMULSIONS, INC. |
| Nov 21, 2024 | 6475-90-001 | WoodTyler | 500 GAL | $3.71 | ERGON ASPHALT & EMULSIONS, INC. |