$2,175.33Avg low bid / CYC
$1,881.62Avg of all bids
$3,213.04Avg engineer's estimate
4Jobs · 115 CYC
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 40 | $3,500.00 | $3,500.00 |
| 2021 | 2 | 56 | $1,592.86 | $1,172.67 |
| 2020 | 1 | 19 | $1,103.34 | $4,701.11 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 1, 2024 | 0168-09-083 | RandallAmarillo | 40 CYC | $3,500.00 | WEBBER, LLC |
| Apr 8, 2021 | 0066-05-065 | MooreAmarillo | 26 CYC | $1,700.00 | SEMA CONSTRUCTION, INC. |
| Apr 7, 2021 | 0016-08-039 | BexarSan Antonio | 30 CYC | $1,500.00 | RELMCO, INC. |
| Feb 6, 2020 | 0275-01-199 | PotterAmarillo | 19 CYC | $1,103.34 | ALLEN BUTLER CONSTRUCTION, INC. |