$1,652.01Avg low bid / EA
$1,994.19Avg of all bids
$1,772.58Avg engineer's estimate
6Jobs · 20 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 2 | $1,100.00 | $2,371.75 |
| 2025 | 5 | 18 | $1,713.34 | $1,868.34 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 2, 2026 | 6498-90-001 | DallasDallas | 2 EA | $1,100.00 | AMERICAN LIGHTING AND SIGNALIZATION, LLC |
| Sep 17, 2025 | 6489-92-001 | BexarSan Antonio | 2 EA | $300.00 | E-Z BEL CONSTRUCTION, LLC |
| Jun 5, 2025 | 6480-71-001 | DallasDallas | 2 EA | $1,803.00 | YUNEX LLC |
| May 8, 2025 | 6478-34-001 | BrownBrownwood | 2 EA | $2,279.60 | WG ENGINEERING & CONSTRUCTION, LLC |
| May 1, 2025 | 6448-25-001 | TarrantFort Worth | 10 EA | $1,700.00 | WG ENGINEERING & CONSTRUCTION, LLC |
| Mar 20, 2025 | 6478-34-001 | BrownBrownwood | 2 EA | $2,537.50 | WG ENGINEERING & CONSTRUCTION, LLC |