$21,292.24Avg low bid / EA
$26,569.76Avg of all bids
$30,307.14Avg engineer's estimate
6Jobs · 7 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 6 | 7 | $21,292.24 | $26,569.76 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 6, 2026 | 0095-03-100 | KaufmanDallas | 1 EA | $1,000.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Aug 5, 2026 | 0089-07-166 | WhartonYoakum | 1 EA | $23,872.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Jul 1, 2026 | 3510-04-066 | Fort BendHouston | 1 EA | $24,160.00 | HARPER BROTHERS CONSTRUCTION LLC |
| Jul 1, 2026 | 2452-03-128 | BexarSan Antonio | 1 EA | $34,113.68 | PULICE CONSTRUCTION, INC. |
| May 6, 2026 | 0073-08-183 | BexarSan Antonio | 1 EA | $23,900.00 | HUNTER INDUSTRIES, LTD. |
| Mar 5, 2026 | 0913-00-136 | De WittYoakum | 2 EA | $21,000.00 | VACA UNDERGROUND UTILITIES INC |