Bid code 628-6083

ELC SRV TY A 240/480 100(SS)SS(E)GC(U) · per EA Sign up free

‹ All bid codes

$5,684.77Avg low bid / EA
$6,754.52Avg of all bids
$6,576.82Avg engineer's estimate
7Jobs · 11 EA

Average low bid by year

YearJobsQuantityAvg lowAvg all
202314$5,100.00$7,527.12
202211$7,560.00$7,895.39
202111$5,425.00$5,920.87
201911$5,507.52$6,440.64
201811$6,275.00$6,872.05
201723$5,788.33$5,270.26

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Jun 27, 20230087-02-055 Jim WellsCorpus Christi4 EA $5,100.00D&G ENERGY CORPORATION
Aug 4, 20220598-02-111 BrazoriaHouston1 EA $7,560.00JAMES CONSTRUCTION GROUP, LLC
Jan 8, 20212524-02-022 BrazoriaHouston1 EA $5,425.00COPASA INC
Feb 5, 20190027-13-212 HarrisHouston1 EA $5,507.52SICE, INC.
May 2, 20180389-05-116 HarrisHouston1 EA $6,275.00WEBBER, LLC
Aug 8, 20170271-17-161 HarrisHouston2 EA $5,575.00WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Apr 4, 20170500-03-107 HarrisHouston1 EA $6,215.00WILLIAMS BROTHERS CONSTRUCTION CO., INC.