$11.77Avg low bid / SY
$23.26Avg of all bids
$30.80Avg engineer's estimate
12Jobs · 33,399 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 1,300 | $8.00 | $10.75 |
| 2022 | 2 | 1,833 | $15.47 | $21.64 |
| 2021 | 2 | 4,916 | $10.68 | $22.71 |
| 2020 | 2 | 22,006 | $10.09 | $21.71 |
| 2019 | 2 | 2,224 | $20.18 | $32.74 |
| 2018 | 1 | 400 | $32.00 | $34.17 |
| 2017 | 2 | 720 | $30.82 | $58.64 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 5, 2023 | 0275-11-090 | GrayAmarillo | 1,300 SY | $8.00 | J. LEE MILLIGAN, INC. |
| Oct 7, 2022 | 0089-10-026 | WhartonYoakum | 1,188 SY | $8.50 | JAMES CONSTRUCTION GROUP, LLC |
| Feb 4, 2022 | 1245-02-049 | PotterAmarillo | 645 SY | $28.30 | KIEWIT INFRASTRUCTURE SOUTH CO. |
| Aug 5, 2021 | 0904-00-197 | PotterAmarillo | 3,255 SY | $10.00 | MASSANA CONSTRUCTION INC. |
| Aug 5, 2021 | 0027-04-042 | WhartonYoakum | 1,661 SY | $12.00 | SJ&J CONSTRUCTION, LLC |
| Oct 2, 2020 | 0168-09-165 | RandallAmarillo | 1,111 SY | $11.70 | J. LEE MILLIGAN, INC. |
| May 7, 2020 | 0904-00-195 | PotterAmarillo | 20,895 SY | $10.00 | HJC FARMS, INC. |
| Nov 6, 2019 | 0185-01-030 | BellWaco | 304 SY | $15.00 | J.D. ABRAMS, L.P. |
| Aug 6, 2019 | 0005-05-114 | HowardAbilene | 1,920 SY | $21.00 | GRATIOT CONSTRUCTION, LTD. |
| Aug 7, 2018 | 0043-08-075 | WichitaWichita Falls | 400 SY | $32.00 | SCR CIVIL CONSTRUCTION, LLC |
| Dec 5, 2017 | 0005-05-109 | HowardAbilene | 240 SY | $52.45 | PRICE CONSTRUCTION, LTD. |
| Aug 8, 2017 | 0005-06-119 | HowardAbilene | 480 SY | $20.00 | MASSANA CONSTRUCTION INC. |