$5,945.89Avg low bid / EA
$6,898.78Avg of all bids
$4,436.67Avg engineer's estimate
4Jobs · 18 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 1 | 5 | $6,670.42 | $7,883.47 |
| 2019 | 1 | 4 | $5,000.00 | $5,320.49 |
| 2018 | 1 | 3 | $5,600.00 | $5,916.67 |
| 2017 | 1 | 6 | $6,145.64 | $7,382.83 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 6, 2020 | 0275-01-199 | PotterAmarillo | 5 EA | $6,670.42 | ALLEN BUTLER CONSTRUCTION, INC. |
| Jan 9, 2019 | 0015-08-142 | WilliamsonAustin | 4 EA | $5,000.00 | DAN WILLIAMS COMPANY |
| May 1, 2018 | 1015-01-023 | RockwallDallas | 3 EA | $5,600.00 | TISEO PAVING CO. |
| Dec 5, 2017 | 0008-13-221 | TarrantFort Worth | 6 EA | $6,145.64 | FLATIRON CONSTRUCTORS, INC. |