$269.04Avg low bid / CY
$285.39Avg of all bids
$292.30Avg engineer's estimate
12Jobs · 2,213.1 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 2 | 90 | $322.17 | $316.69 |
| 2020 | 1 | 93 | $422.49 | $399.50 |
| 2019 | 1 | 16 | $600.00 | $1,026.67 |
| 2018 | 4 | 473 | $251.22 | $267.28 |
| 2017 | 3 | 869 | $201.03 | $283.12 |
| 2016 | 1 | 672.1 | $333.28 | $277.45 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Dec 2, 2021 | 3075-01-011 | GoliadCorpus Christi | 78 CY | $316.35 | J. CARROLL WEAVER, INC. |
| Mar 17, 2021 | 6376-05-001 | AtascosaSan Antonio | 12 CY | $360.00 | SJ&J CONSTRUCTION, LLC |
| Jun 4, 2020 | 6363-48-001 | ReevesOdessa | 93 CY | $422.49 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
| Apr 3, 2019 | 0076-01-029 | PecosOdessa | 16 CY | $600.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Jul 11, 2018 | 0902-20-111 | WiseFort Worth | 122 CY | $288.00 | PIERCE R & B LLC |
| Jun 5, 2018 | 0924-00-099 | El PasoEl Paso | 184 CY | $260.00 | DAN WILLIAMS COMPANY |
| May 1, 2018 | 0139-04-045 | ReevesOdessa | 2 CY | $683.14 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Apr 4, 2018 | 0902-40-027 | JackFort Worth | 165 CY | $209.00 | PIERCE R & B LLC |
| Aug 8, 2017 | 0139-03-039 | ReevesOdessa | 128 CY | $400.00 | FNF CONSTRUCTION, INC. |
| Aug 8, 2017 | 0327-10-057 | WillacyPharr | 441 CY | $178.00 | FOREMOST PAVING, INC. |
| Jan 4, 2017 | 0385-04-045 | HoodFort Worth | 300 CY | $150.00 | BRETT CONSTRUCTION COMPANY |
| Nov 3, 2016 | 0902-90-067 | TarrantFort Worth | 672.1 CY | $333.28 | MCMAHON CONTRACTING, L.P. |