$45.75Avg low bid / SF
$51.35Avg of all bids
$67.17Avg engineer's estimate
4Jobs · 526,419 SF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 268,175 | $41.65 | $47.40 |
| 2025 | 1 | 258,244 | $50.00 | $56.45 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 6, 2026 | 3510-04-069 | Fort BendHouston | 23,866 SF | $52.44 | JAMES CONSTRUCTION GROUP, LLC |
| Aug 5, 2026 | 0089-07-166 | WhartonYoakum | 195,749 SF | $40.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Jul 1, 2026 | 3510-04-066 | Fort BendHouston | 48,560 SF | $43.00 | HARPER BROTHERS CONSTRUCTION LLC |
| May 2, 2025 | 0665-02-004 | El PasoEl Paso | 258,244 SF | $50.00 | DAN WILLIAMS COMPANY |