$95.71Avg low bid / TON
$99.03Avg of all bids
$91.78Avg engineer's estimate
15Jobs · 541,941.1 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2019 | 7 | 263,356.15 | $101.61 | $107.53 |
| 2018 | 6 | 206,611.95 | $89.55 | $97.96 |
| 2017 | 2 | 71,973 | $91.76 | $88.71 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Dec 3, 2019 | 0052-01-042 | ParmerLubbock | 33,155.15 TON | $117.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Jun 5, 2019 | 0461-05-011 | Yoakum | 52,559 TON | $115.00 | DUININCK, INC. |
| Jun 4, 2019 | 0380-01-092 | LubbockLubbock | 7,483 TON | $97.54 | ALLEN BUTLER CONSTRUCTION, INC. |
| Apr 3, 2019 | 0145-05-032 | HaleLubbock | 4,981 TON | $135.00 | DUININCK, INC. |
| Mar 6, 2019 | 0168-01-030 | ParmerLubbock | 98,943 TON | $95.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Mar 5, 2019 | 1905-01-009 | DawsonLubbock | 10,826 TON | $125.00 | A. L. HELMCAMP, INC. |
| Feb 5, 2019 | 0880-04-032 | LubbockLubbock | 55,409 TON | $84.50 | ALLEN BUTLER CONSTRUCTION, INC. |
| Jun 5, 2018 | 0227-06-026 | HockleyLubbock | 26,106.54 TON | $107.00 | A. L. HELMCAMP, INC. |
| Jun 5, 2018 | 0461-08-023 | Yoakum | 42,670 TON | $90.00 | JAMES HAMILTON CONSTRUCTION CO. |
| May 1, 2018 | 0168-01-029 | ParmerLubbock | 76,258.18 TON | $77.85 | J. LEE MILLIGAN, INC. |
| Apr 4, 2018 | 0226-06-032 | CastroLubbock | 42,024 TON | $94.95 | J. LEE MILLIGAN, INC. |
| Apr 3, 2018 | 0227-06-024 | HockleyLubbock | 16,011.23 TON | $103.04 | ALLEN BUTLER CONSTRUCTION, INC. |
| Mar 7, 2018 | 0453-02-018 | CrosbyLubbock | 3,542 TON | $82.17 | ALLEN BUTLER CONSTRUCTION, INC. |
| Feb 2, 2017 | 0380-06-017 | DawsonLubbock | 35,479 TON | $96.98 | REECE ALBERT, INC. |
| Jan 5, 2017 | 0068-01-069 | LubbockLubbock | 36,494 TON | $86.69 | ALLEN BUTLER CONSTRUCTION, INC. |